From:
Sent: Thursday, January 27, 2011 4:24 PM
To: Jeffrey Epstein
Subject: Fwd: Island - June
Begin forwarded message:
From: "Gary Kerney"
Date: November 19, 2010 10:29:34 AM =ST
To: "Jeffrey Epstein" <[email protected]>
Cc:
=/div>
Subject: FW: Island - =une
From: Gary =erney
Sent: Mon 6/14/2010 10:10 AM
To: =helley
Subject: RE: Island - June
Shelley no attachment Gary
From: Shelley =
Sent: Sun 6/13 . -
To: Jeffrey Epstein
Cc: Story Cowles; Gary =erney; Doug Schoettle
Subject: Island - June =br>
Hi all,
Gary did a great job of putting this together. I've added some =omments below and the specific things I'm taking
care of in a separate =mail.
Thank you,
EFTA_R1_00142861
EFTA01801688
Shelley
PLANS
Pick up latest marked drawings from Robert's =ffice on Tuesday 15th, will make copy and send to Doug this
=eek.
DOCK
See attached =mage.
LIBRARY
Status interior
1.interiors complete =y construction
Outstanding issues
1.ceiling treatment =nbsp; Ion to visit week after next to start =ainting - work duration 2- 3 weeks - estimated
completion date =uly 8th
2.cabinet finishes =nbsp; awaiting panel from =aris, delay now due in this week by the =9th
3.floor =inishes le to decide on =ext visit to Island, decision made by July =st.
Status exterior
1.courtyard paving =nderway complete by the July 31
2.irragation main line =nderway complete by July 15
3. wall sconces to replace existing, will get =nfo on them from Robert's =ffice
Outstanding issues
=.landscape plans
=.plants 'gala to fill in =rea behind tiki hut with plants we chose awaiting new images from =im
=.irragatiion =tans
=.lighting will send sample =ighting options via email this =eek
2.Igala =as trees tagged ready for delivery as soon as barge is =eady
MASTER SUITE
2
EFTA_R1_00142862
EFTA01801689
Status interior
1.const under =ay ,subject to decisions being made should finish by Oct =1
Outstanding issues
1.steam =ench
2.out side =hower
3.lites over =ed
4.lighting in =edroom
S.electrical in =ath area
6.tub deck and =urround
7.selection =f wood floor
8.sourcing =hassos slabs
9.powderroom =anity plan
10.shop drawings for =tone
11.order rug for =athroom
Status exterior
1.wall under =ay, complete by Aug 31
Outstanding issues
1.landscape irr.
KITCHEN
Status
1.assume we get =ermit by July 1 should be complete by Nov.31
Outstanding issues
1.kitchen resign
2.stair and =all design to master
LAUNDRY
1.assume we get =ermit July 1 should complete by Oct 31
COTTAGES
1.const underway =hould complete by Sept =0
Outstanding issues
1.shower =esign
Other guest =ottage to be built in same complex: revisit idea on next =isit
3
EFTA_R1_00142863
EFTA01801690
MAIN HOUSE REMODEL
Status no estimate to =ompleation til program complete
1.courtyard side =Ian final,proceeding
2.roofing =roceeding
Outstanding issues
1.north side =rogram
MECHINICAL =LECTRICAL Status under way =hould complete by Sept 30
MECHANICAL DESAL Status under way =hould complete by Nov 30
POOL/THEATER
=.Gensler allow three months for plans
=.two months for permits Nov 30
3.pool by Mar =1
theater by Jun 30
4
EFTA_R1_00142864
EFTA01801691
ℹ️ Document Details
SHA-256
bf6cf07e29b776a7b1704aeb7a5f08101731d4b673d84ce97631a31261eeda39
Bates Number
EFTA01801688
Dataset
DataSet-10
Type
document
Pages
4
💬 Comments 0