Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:10484
Region: NER Month Code: 10 Institution: NYM
Project #: Title: 2D3S Remove Asbestos
Approval: 7/18/2019 Expiration: 7/18/2022
Funding
Fiscal Year Funded: 2019 Allotted: $100,000.00
Percent Obligated: 0% Obligated: $0.00
Unobligated: $100,000.00
Construction Status
Completion Percentage: 01% Progress Status: On Schedule
Est. Completion: 7/18/2022 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 2.00 S&E ManHours this Month: 2.00
Total S&E and B&F ManHours: 2.00 Estimated Hours: 600
Detail Check List
❑ A&E Services required.
O New construction will result in capitalization of a building or other structure.
O Renovation will result in capitalization of an improvement to an existing building or other structure.
El Asbestos Abatement is required or has been completed.
O ESPC or UESC funded
O FITARA process is required.
Funding
Fiscal Year Funded: 2019 Allotted: $120,320.00
Percent Obligated: 0% Obligated: $0.00
Unobligated: $120,320.00
Construction Status
Completion Percentage: 01% Progress Status: On Schedule
Est. Completion: 7/25/2022 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 1.00 S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 1.00 Estimated Hours:
Detail Check List
❑ A&E Services required.
O New construction will result in capitalization of a building or other structure.
O Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
O FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D3U Replace PBX - Project Approval Received 7/25/19. Procurement Documents Initiated.
Facility Manager: AW:
Page 1 of 9
EFTA00142424
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:6633
Region: NER Month Code: 10 Institution: NYM
Project #: 2C4G Title: 2C4G Replace Doors Phase 2
Approval: 6/7/2017 Expiration: 6/7/2020
Funding
Fiscal Year Funded: 2017 Allotted: $116,746.48
Percent Obligated: 96.3219% Obligated: $112,452.48
Unobligated: $4,294.00
Construction Status
Completion Percentage: 61% Progress Status: On Schedule
Est. Completion: 6/7/2020 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 254.00 S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 254.00 Estimated Hours: 3,705
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
Ri Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C4G Replace Doors Housing Unit Phase II -
Number of Doors Installed This Month - 0
The Doors Were Installed On Unit -
Staff Hours Used This Month - 0
Cost of Materials Used This Month - $0
Number of Doors Left to Install On This Project - 14
Facility Manager: AW:
Page 2 of 9
EFTA00142425
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:6926
Region: NER Month Code: 10 Institution: NYM
Project #: 2C4T Title: 2C4T Repair Food Service Coolers
Approval: 7/29/2017 Expiration: 7/29/2020
Funding
Fiscal Year Funded: 2017 Allotted: $15,200.00
Percent Obligated: 72.772% Obligated: $11,061.35
Unobligated: $4,138.65
Construction Status
Completion Percentage: 17% Progress Status: On Schedule
Est. Completion: 7/29/2020 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 17.00 S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 17.00 Estimated Hours: 180
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
❑ Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C4T Repair Food Service Coolers -
Staff Hours Used This Month: 0
Tasks Completed This Month: Revised plan for placement of future condensate unit and how the lines will be run
Tasks Left to Complete: Install Units, Run Lines
Plan Going Forward: Staff will mount units, then we will determine necessity for contractors
Facility Manager: AW:
Page 3 of 9
EFTA00142426
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:7247
Region: NER Month Code: 10 Institution: NYM
Project #: 2C5N Title: 2C5N Replace Food Service Trough
Approval: 10/23/2017 Expiration: 10/23/2020
Funding
Fiscal Year Funded: 2018 Allotted: $12,000.00
Percent Obligated: 40.233% Obligated: $4,827.97
Unobligated: $7,172.03
Construction Status
Completion Percentage: 99% Progress Status: On Schedule
Est. Completion: 10/23/2020 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 43.00 S&E ManHours this Month: 0.50
Total S&E and B&F ManHours: 43.00 Estimated Hours: 112
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
❑ Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C5N Replace Food Service Trough - All financial obligations have been met. Financial closure submitted.
Awaiting NERO business office.
Facility Manager: AW:
Page 4 of 9
EFTA00142427
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:8437
Region: NER Month Code: 10 Institution: NYM
Project #: 2C6Z Title: 2C6Z MTA-Lead/Asbestos Removal MTA
Approval: 5/16/2018 Expiration: 5/16/2021
Funding
Fiscal Year Funded: 2018 Allotted: $2,460,000.00
Percent Obligated: 99.844% Obligated: $2,456,164.60
Unobligated: $3,835.40
Construction Status
Completion Percentage: 75% Progress Status: On Schedule
Est. Completion: 5/16/2021 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 60.00 S&E ManHours this Month: 8.00
Total S&E and B&F ManHours: 60.00 Estimated Hours: 2,400
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
Ei Renovation will result in capitalization of an improvement to an existing building or other structure
•
El Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C6Z MTA-Lead/Asbestos Removal MTA-
Type of Work Conducted This Month - Demolition: Removed 4 turbines, 1 tank, 1 switch
Staff Hours Used This Month - 8
Cost of Materials Used This Month - 0
Anticipated Time Left On This Project - 2 months
Next Anticipated Work Type - Demolition: Remove Remaining Switches and Demo Turbines
Facility Manager: AW:
Page 5 of 9
EFTA00142428
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:8282
Region: NER Month Code: 10 Institution: NYM
Project #: 2C8L Title: 2C8L Replace Basement Elevator Saddle
Approval: 5/17/2018 Expiration: 5/17/2021
Funding
Fiscal Year Funded: 2018 Allotted: $45,000.00
Percent Obligated: 97.6091% Obligated: $43,924.10
Unobligated: $1,075.90
Construction Status
Completion Percentage: 99% Progress Status: On Schedule
Est. Completion: 5/17/2021 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 25.00 S&E ManHours this Month: 0.50
Total S&E and B&F ManHours: 25.00 Estimated Hours: 40
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
❑ Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C8L Replace Basement Elevator Saddle-
Preparing documents for financial closure.
Facility Manager: AW:
Page 6 of 9
EFTA00142429
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:8438
Region: NER Month Code: 10 Institution: NYM
Project #: 2C8V Title: 2C8V Repair Roof
Approval: 6/14/2018 Expiration: 6/14/2021
Funding
Fiscal Year Funded: 2018 Allotted: $76,000.00
Percent Obligated: 92.413% Obligated: $70,233.91
Unobligated: $5,766.09
Construction Status
Completion Percentage: 99% Progress Status: On Schedule
Est. Completion: 6/14/2021 Completed: 8/13/2019
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 17.00 S&E ManHours this Month: 1.00
Total S&E and B&F ManHours: 17.00 Estimated Hours: 425
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
❑ Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C8V Repair Roof- Project work completed, awaiting Financial Closure. Financial Closure submitted to Financial
Management on 4/23/2019.
Facility Manager: AW:
Page 7 of 9
EFTA00142430
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:9580
Region: NER Month Code: 10 Institution: NYM
Project #: 2D2P Title: 2D2P Emergency Replace Heating Coils
Approval: 2/8/2019 Expiration: 2/8/2022
Funding
Fiscal Year Funded: 2019 Allotted: $99,500.00
Percent Obligated: 24.1778% Obligated: $24,057.00
Unobligated: $75,443.00
Construction Status
Completion Percentage: 66% Progress Status: On Schedule
Est. Completion: 2/8/2022 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 102.00 S&E ManHours this Month: 2.00
Total S&E and B&F ManHours: 102.00 Estimated Hours: 800
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
❑ Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D2P Emergency Replace Heating Coils
Equipment Replaced This Month -
The Equipment Services -
Staff Hours Used This Month - 2
Cost of Materials Used This Month - $0
Equipment Left to Replace On This Project - Condensate Pumps, AHU Motors, In-Duct Coils
Next Anticipated Equipment Replacement Site Is - Condensate Pumps
Facility Manager: AW:
Page 8 of 9
EFTA00142431
Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019 WO #:10473
Region: NER Month Code: 10 Institution: NYM
Project #: 2D3N Title: 2D3N Construct Gun Locker
Approval: 7/17/2019 Expiration: 7/17/2022
Funding
Fiscal Year Funded: 2019 Allotted: $200,000.00
Percent Obligated: 0% Obligated: $0.00
Unobligated: $200,000.00
Construction Status
Completion Percentage: 05% Progress Status: On Schedule
Est. Completion: 7/17/2022 Completed:
Staff Man Hours
Total B&F ManHours: B&F ManHours this Month:
Total S&E ManHours: 8.00 S&E ManHours this Month: 8.00
Total S&E and B&F ManHours: 8.00 Estimated Hours: 1,920
Detail Check List
❑ A&E Services required.
❑ New construction will result in capitalization of a building or other structure.
❑ Renovation will result in capitalization of an improvement to an existing building or other structure.
❑ Asbestos Abatement is required or has been completed.
❑ ESPC or UESC funded
❑ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D3N Construct Gun Lockers - Project Approval Received 7/17/19. RCA Packet prepared and sent for approval
7/26/19.
Facility Manager: AW:
Page 9 of 9
EFTA00142432
ℹ️ Document Details
SHA-256
c520db9b426455141e6193434364781ef0d55f606fff6703baadb052e141cbcf
Bates Number
EFTA00142424
Dataset
DataSet-9
Document Type
document
Pages
9
Comments 0