📄 Extracted Text (615 words)
Punch List — per JE directives as of January 24. 2012
1. Rug — date?
2. Flagpole bath and cabana — plastic door pushes ordered. Slipcovers for sofa and cushions in production
Stero cabinets estimate due this week. Walkway gates latches to be installed, self closers
3. Info Center — looking into remote that can control all 5 fans
- Dock Box — pending available time
4. Five Palms — stucco, window, hardscape, electrical
5. Grotto — lookout built with metal roof, landings
6 .Greenhart wood — steps to Grotto
7. Heli wall
8. Heli garage.
9. Hangar —floor sanding in progress — 401)(50' area for slab, 3 foot wall around it — containment for ISO
fuel tank — bathroom and room divider — subcontractor
10. Steel shed have estimate for building, budget to be forwarded 31Jan
11. Triangle, commenced work
12. Entry tree lights, confirmed ground lighting
13. Pebble beach - Solar fridge, light, fan for pebble beach.
14. Library Dehumidifaction 2nd unit ordered, Sarah office damper needs new board, invoicing issue still need
to sorted out
15. Yellow flowering Alamandra up Old Mill wall and Flagpole hill Peter to train vines to wall
16. Solutions for generators —drawings complete for bid package
17. Fire system — need to review operational and maintenance schedule
18. Top of hill — CLEAN UP - place garbage in circle — build up 10 feet — new helipad
19. Pool — heaters relocation work started, flag pool started
20. Library windows Done
21. Five Palms
- Floor
- Doors location and fabrication
-Lighting schedule
27.
28. Tree transplants
30. Guestroom -
Cabana 3 leaks, Cabana 1 leaks Main terrace — sealing of gutters in progress
31. Tiki
- Shields due end of the month
- Dock box pending available time
32. Sunken garden berm continues
33. Concrete roads at flagpole
34. Concrete triangle
35. Compass
36. Bench placements —bench on peninsula point
37. Engineering clean up continues
38. New vehicles
39. Dock Decking Samples layed
40. Shower doors awaiting replacement glass, chilax rm
41. Lighting-adjust landscape lights at night,
42. Aquarium photo Commence 13 Feb
43. Waterfall bottom done
EFTA01107319
44. Mgrs Cottage Roof work remains
45. Master bath - leaks
46. Mooring Permit At Army Corp
47. Permits —guest house. Done
48. Electrical quotes ????
49. Top of hill Clean up continues
50. Rationalize Telephone system Bill and Steve due LSJ 27th to 29th Jan
51. Rock grinder Purchased
52. Outdoor bath — New handheld purchased
53. The rock crusher, the dirt sifter, and the cement plant should all be operating at full capacity — 1/19/2012
54. Gates to hide engineering both at top and bottom of hill. Bill reviewing light weight gates.
55. Engineering service road reshaped. Continues
56. Dock lighting -Barn lights for structures, spots for dock and barge ramp on remote
57. Dock house completed except for final electrical
58. Roads — from intersection to Flagpole
59. Guest house — site layout needs to be confirmed
60. Chillax room — furniture piece required for electrical/media equipment
61. Library Beach sand in place
62. Entry band completed
63. High gloss polyurethane deck finish applied to nautilus shells 30th
64. Replacement transformer Mechanical building. Reviewing bids, will submit for approval 1 Feb
65. Photos for Chillax bath — installed
66. Towel rack for Master Installed
67. Let Jules and Peter bulldoze road now from top of hill down towards Flagpole Done
68. Floating Dock, new design to be submitted rd Feb
69. Remove Rusty metal dock Columns. Reviewing options
70. New Lull will forward options next week
71.
72. Fat Cat- inspection completed, buyers contacted
73. Big N- inspection today
74. Midnight Express repairs complete
EFTA01107320
ℹ️ Document Details
SHA-256
c954bff712b38a83ba52ce408d03e3405f79d463c3731f8484b630234f2f8b3d
Bates Number
EFTA01107319
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0