📄 Extracted Text (648 words)
From: J <[email protected]>
To: Brice < >, Rich Kahn
Subject: Fwd: Cabana Bathroom Tile
Date: Mon, 19 Nov 2018 14:52:11 +0000
Why the counter top delay?!
Forwarded message
From: Kyle reavis
Date: Mon, Nov 19, 2018 at 9:39 AM
Subject: Re: Cabana Bathroom Tile
To: jeffrey E. <[email protected]>
No sir, the sinks are under mounted so the counter top guys will be installing cabana 1 tomorrow. Then they are
moving to the flag pole to do those tops, then moving to cabana 2,3, then 4. Brice and said that work
sequence was approved by you previously, if you want it changed please let me know. Counter tops are going to
be finished by first week in December is what I was told this morning. Cabana 1 will be up and operational by
the 23rd.
On Mon, Nov 19, 2018 at 10:29 AM J [email protected]> wrote:
So is entite cabans complete bathroom sinks fixtures all by 23
On Mon, Nov 19, 2018 at 9:26 AM Kyle reavis < > wrote:
Good Morning Mr Epstein,
JPK will be wrapping up tile in cabana 1-4 today with the finished fixtures to be screwed in place tomorrow.
The tile has gone slow due to the number of cuts they need to do with small showers and 2'x2' tiles. The
men have been working non-stop all weekend to make sure they wrap this up for you. Shower doors are still
on schedule to be in SST the 23rd. The only area that will be left are the shower door frames which will be
removed after the glass is installed in the windows. Please let me know if you have any questions and I
apologize for the delay.
Very Respectfully,
Kyle Reavis
On Tue, Nov 13, 2018 at 3:08 PM Kyle reavis wrote:
Good Afternoon,
Please see tile and final sequence of events for cabana bathrooms;
Cabana 1:
14th - Demo bench, set all floor tiles, plaster ceilings
15th - Tile walls (all day) - Finish tile
16th - Toilet Install / Lighting install
Awaiting Shower door delivery (23rd estimated)
Window can receive Plexiglas in place of privacy glass to seal showers interim
Cabana 2:
14th - set floor tiles , plaster ceilings
EFTA01016238
15th - Install toilets
16th - tile walls (all day) - Finish Tile
17th - Lighting Install
Awaiting Shower door delivery (23rd estimated)
Window can receive Plexiglas in place of privacy glass to seal showers in interim
Cabana 3:
14th - set floor tiles , plaster ceilings
15th - install Toilets
16th - Lighting Install
17th - Tile Walls - Finish Tile
Awaiting Shower door delivery (23rd estimated)
Cabana 4:
14th - seal exterior door, plaster ceilings , set floor tiles
15th - Install toilets
18th - Wall tile Install (all day) - Finish
19th - Shower door Install
Very respectfully,
Kyle Reavis
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01016239
ℹ️ Document Details
SHA-256
cabfec68adb9304a61f13d47aa2a68669097b4f3689312ef768e532aa6e7ee01
Bates Number
EFTA01016238
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0