(ConocoPhillips Optimized Cascade
Process)
• Bechtel has built one-third of
the world's liquefaction plants, is
currently ahead of the guaranteed
construction schedule for the first four
trains of (with the first two trains
complete), and previously built the
Sponsor's existing regasification
facilities at the Sabine Pass LNG
terminal on time and within budget.
Bechtel has never been called to pay
delay or performance Liquidated
Damages
Elba The project is an expansion of an • Fixed price, lump sum, date-
existing facility — infrastructure certain EPC Contract with delay
interconnections and LNG storage Liquidated Damages.
tanks are already in place. The Project's • Backstopped by parent
construction is currently 35% guaranty from IHI (Japanese Corp
complete. Rating of A-) for full payment and
performance and letter of credit for
12.5% of contract price
• EPC work is generally
mechanical in nature and IHI is a
reputable and experienced EPC
Contractor (worked on other LNG
projects worldwide, including Gulf
LNG, Cove Point, Adriatic LNG, and
more)
• The Project has a budgeted
contingency of $41.7 million and a key
Kinder Morgan (joint owner)
subsidiary has pledged to fund an
additional $68.0 million in cost
overruns, with no dilution to the
Borrower.
• Kinder Morgan and the
Borrower are committed to providing
an additional $62.6 million on a pro
rata basis, resulting in a total
contingency amount of $172.3 million,
well above the independent
engineer's identified target amount of
$86.5 million
CONFIDENTIAL - PURSUANT TO FED. R. CRIM. P. 6(e) DB-SDNY-0090786
CONFIDENTIAL SDNY_GM_00236970
EFTA01387694
ℹ️ Document Details
SHA-256
cb094283bd2a9ed2c08aac6b8f25169a173dcd376c0a1e3195205e8127bdb964
Bates Number
EFTA01387694
Dataset
DataSet-10
Document Type
document
Pages
1