From: Lvjet <lvjet@aolcom>
Sent: Tuesday, March 15, 2016 6:26 PM
To: [email protected]; [email protected]
Subject: B727 Mx july
Jeffrey
I met with Morrison today, we discussed the upcoming B727 Mx visit,.
its our Heavy C check for July 1st,.
which includeds 2c 3c 4c and Aux tank removal 2c 1200 man hours
3c1800 man hours
4c 2500 man hours
tank removal 1800 man hour
total 8900 man hours x Shop rate Stambaugh $50.00 to $100 Associated which is the best.
$50 x 8900 = $445,000 plus 1.75 for repair items found = $778,750
$100 x 100 = $890,000 plus 1.75 for repair items found = $1,557,500
this Mx event could hit $2M if major corrosion is found,.
thx
Larry