From: Daphne Wallace
Sent: Friday, June 19, 2015 1:44 PM
To: Jeffrey Epstein
Cc: ann rodriquez; Rich Kahn
Subject: Barge return - June 19, 2015
Greetings Sir,
The realistic date for t=e return of Big N is Friday, July 31.
We spoke wi=h Gene this morning (Gene spoke with Boscoe last night) who summarized for=us the parts to be
completed before the barge is ready for sea trials:
Old engines removed and stored
Engine parts=swapped from old engines to new ones New engines set in pl=ce (old engines loaded for return) Alignment
Exhaust s=stem Wiring to the new engines Recondition the transmi=sion Replace the fuel lines Recondition the
fuel=filters Sea trials
Gene does not forese= any catastrophic setbacks, but at this time he also does not see the comp=etion before the end
of July.
When we speak with =oyson on Monday, I will request their barge for the mobilization of Better=Roads equipment, and
that they work with us as auxiliary until Big N's=return, so this project's schedule is not derailed.
Respectfully, Daphne
EFTA_R1_01623579
EFTA02498267
ℹ️ Document Details
SHA-256
d42c1b915d55e1f83e657bcb84750e6464837632369245fdc334d1516fe462cd
Bates Number
EFTA02498267
Dataset
DataSet-11
Type
document
Pages
1
💬 Comments 0