From: David Mitchell.
To: Jeffrey Epstein [email protected]>
Subject:
Date: Wed, 02 May 2018 12:30:35 +0000
Update on TCO , working completing this list TODAY
Please see the below sign offs needed for Grant to complete the TR1 forms, which will be the remaining
paperwork to obtain TCO for 19 West 31 Street. Grant has requested the below in order to complete the TRI
forms:
1. Structural - the walls/ceilings closed up, not possible for an inspection; therefore, need the structural
engineer to sign off on all nonconformities. The structural engineer needs to approve work completed. EWA
WORKING ON LIST
2. Sprinkler system - no submittals on site / The MEP engineer needs to sign off on the installed sprinkler heads
and confirm the installed sprinkler heads were per the submittals. GRANT CONFIRMING LOCATION OF
PHOTO
3. Masonry anchors - the walls/ceilings closed up, not possible for an inspection; therefore, need the
structural engineer to approve the SOP conditions and if possible, have the GC provide photos and info on
installation. EWA TO CONFIRM
fre4d-tyorleeon-kffms-ii:)-,..ipeeifittt+iorts7
SrFife-proteetion—tieetlghe-DGB,LFDN.NLsign-e.ffi-front-Meitopeliso9r.GREleetrieal7
6. Mechanical - then one last item, Grant inspector needs to do the final Mechanical inspection.
DAVID MITCHELL
Mitchell Holdings LLC
EFTA00820379
ℹ️ Document Details
SHA-256
d60de3b0cda20d1658562ba3021c7318594423d106cd14122b68a5c163392d66
Bates Number
EFTA00820379
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0