LSJ CONSTRUCTION
Subcontractor Payout
Project: Mechanical Desal February 3, 2011
Trade: Water System
Requisition #05
Subcontractor TSG Technologies, Inc
Insurance ex iration: March I, 2011
Invoice # Requisition #05
Phase # 11-200
Original Contract Sum: $592,160.00
Change Orders Submitted & Approved: $6,905.00
New Change Orders: $0.00
Total Work Contracted to Date: $599,065.00
Total Work Completed to Date: 95% $569,457.00
Less Retainage: $0.00 /
Total Payments Made to Date: $533,944.00 ‘,/
Total Current Payment Due: $35,513.00 OF
Balance to Finish including Retainage: $29,608.00
Sales Tax Liability:
a. Subcontractor/Supplier is liable, explailinstall only / tax
included in contract
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company:
d. Shipping None
Total Outlays for this contract incl. Sales or Use Tax: $569,457.00
JEE approval attached Invoice Attached
YES NO YES NO
X X tt
Submitted Bill Approved by: Gary
Signed: // Signed:
,4
Date: February 3, 2011 Date: February 3, 2011
Approved by: Emad Approved by:
Signed: Signed:
Date: )191 (( Date:
Is I '
EFTA00609205
LSJ CONSTRUCTION
Project Mechanical Desal
krOcontractor • rue legal name TSG Trecnnotogien Dale Revised Fkon.ingy 3. 2011
Phases 11.200
Trade Water System
'mace I Requisition 405
11
Insurance ealaration I 444, Payment
Para] Final
X
Invoice/Re:14 Dale C/O Amount Retainage Due Paid Date Paid Check?, Balance I
Contract Amount 12/22/69 592.10000
COat 10.11/10 Watch Guard SYSIere 1.000 00
C002 10:13/to Storage / Insurance 1000 00
C003 01118el 1 Lost time 4.905.00
C004
C045
Requisition et 0202/10 Doman RSOCO - 8% 47.80000 000 47 900.00 47,800 0047 1
. 000
Requisition #2 033/30//0 Procurement - 42% 248.280 00 000 248,280.00 248.280 60a/ ...,. 000
Reguitition /3 08/05/10 Ready to Ship. 30% 177.648 00 000 177,048Q9_ 177.648 Unt
ie'?" 0.00
Remmition 44 12/20110 Equip. on Site - 10% 60.216.00 0.00 60.216.00 60.216 00 000
Requisition e5 02103/11 Subsumes' COmpluton - 594_ 79.608 00 000 29,608.00 29,608 00
02/03/11 CO's #2. 43 5.905.00 0.00 5,905.00 5.90500
Rkque.$000 *6 Final Completion • 5%
70101 569,457 00 000 569.457.00 533.944.00 35.51300 I
Contract Amount Phase
Convect RO Plant 592,160 00
con Watch Guard 1.00000 Descnotion
con Storage / Insurance 1,000 00 Da stnption
C013 Lost time 4.90500 Description
CON Description
CO'S Descnotion
Cootraccoo To Date 599.065 00
Balance of Contract Ye/Retainer 29.608 00
EFTA00609206
TSG TECHNOLOGIES. INC. 40-204-02-PRP05
k lbA
e
a TES
wag nu• MO two
Little St. James
Name Use I James. LL amnia Number 40-204-02-PRM0S
Cab Financial Trust Company. kV Dale 2/3/2011
Address 6100 Red Hook Quarter 8.3 Order No.
City SI Thomas TSG Contact Bob Petersen
State USVI Zip 00802 Michael Malo
Phone (340)7798054 Phone (340) 776-7766
Ann Gary Kerney Fax (3401774-9489
Una Price Extended Price -'r
1 Pay Request IS 529 608 00
i Change Order 42 51.000 00
1 Change Cutler //3 S4.905 00
Payment Schedule:
a Task Percentage Payment
I Design Phase- NIP -1 8% 547.800.00
2 Begin Procurement - NIP 2 42% $248.280 00
3 Ready to Ship 30% 5177.648.00
Change Order at $1.000.00
4 Equipment on Site 10% $59.21600
Change Order 42 $1.00000
Change Order 43 54.905 00
5 Substantial Completion 5% 529.608 00
6 Final Compilation 5% 529.608 00
Total 100% $599 065 00
Total per Contract: $599,065.00
Loss Previously Invoiced: $533,944.00
Total this Invoice: $39513.00
Remaining Contract Value: $29,608.00
Subtotal $35.513.00
1/(ve,/,„ Shipping and Handling
Taxes Sono
A .'(7 Total invoice amount $35,513.00
Were information:
TSG Technologies. Inc.
Darby Bank and Trust
EFTA00609207
'moor
TSG
MAKIDG (VERY DROP CUNT
TO Gary Kerney DATE: October 13. 2010
LSJ LLC
FROM: TSG Technologies
CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME: Little St. James RO
PROJECT NUMBER: 40-204-02
ORIGINAL CONTRACT SUM $ 592.160.00
(Contract Dated - February 11, 2010)
PREVIOUSLY APPROVED CHANGE ORDERS $ 1 000 00
(Total Number of Approved Change Orders- 1)
REQUESTED CHANGE ORDER NO. 2 $ 1 000 00
TOTAL 594 160 00
Description of Request (Include time, schedule, authorizing associate)
Item 1: Sloragehnsurance for RO equipment through December 2010 $1.000
TSG TECHNOLOGIES LLC
Att-L-AL:
Page I dl
EFTA00609208
'TSG
S PARKING (VERY DROP COOT
TO: Gary Kerney DATE January 18. 2011
L S.J LLC
c/o Financial Trust Company. Inc
FROM: TSG le_c_hnolockes
CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME. Little St James RO
PROJECT NUMBER: 40-204.02
ORIGINAL CONTRACT SUM $ 592.160.00
(Contract Dated - February 11. 2010)
PREVIOUSLY APPROVED CHANGE ORDERS $ 2.000 00
(Total Number of Approved Change Orders- 2)
REQUESTED CHANGE ORDER NO. 3 $ 4 905 00
TOTAL .$ 599.065 00
Description of Request (include time, schedule, authorizing associate)
Item 1: Time lost due to power not being available to TSG stall as of 1/19/11. Newest information
conveyed to TSG has power available al end of day 1/21/11. for a loss of 3 days.
Installers: 2 people x 9 hrs/day x $50/hr x 3 days 52.700
Project Manager: 1 person x 9 hrs/day x $65/hr x 3 days $1.755
Per Diem: 3 people x $50/day x 3 days $450
If work cannot be completed by 1/28/11. TSG's original finish date. Then extra charges will be incurred for
housing and change ticket fees.
TSG TECHNOLOGIES LS.J., LLC
Page I ol I
EFTA00609209
Emad Hanna
From: Monique Harry
Sent: Friday, Februaris i tr1.12 1 P M.
To: Emad Hanna
Subject: TSG
Attachments: TSG Req 5.pdf
Emad,
Attached for payment TSG Technologies, Inc Req 5 in the amount of $35,513.00. Project 1010 Code 11-200.
Monique
1
EFTA00609210