LSI Dock
Scope of work:
Demo and remove the following
1. Existing Dock Bumpers
2. Existing S/S Fasteners
Straighten and or Install New Bumper fasteners where needed
Remove all existing Bumpers and Paint Dock siding with Epoxy Grey Paint
Replace bumpers.
LSJ to provide floating dock to perform work
Duration: 22 days, 2 Men
JSJ Cottage Bathroom
Scope of Work
Install New Dura Rock in Staff Cottage Bathroom
Duration: 3 Days, 2 Men
Labor Cost
Brian: $300.00 per day @ 25 days = $7500.00
Buck: $120.00 per day @ $25 days = $3000.00
Total Labor Cost: $10,500.00
All material and tools supplied by Owner.
EFTA00804938