📄 Extracted Text (923 words)
From: "Jeffrey E." <[email protected]>
To: Ann Rodriquez •
Subject: Re: Ken Floyd: VI Paving
Date: Fri, 09 Jun 2017 17:58:24 +0000
itemized list assuming no interuptions or privacty needed
On Fri, Jun 9, 2017 at 11:55 AM, Ann Rodriquez -4 > wrote:
Pm sorry Bossman,
You would like for Ken to give us an itemized list with pricing and a timeline from start to finish or you don't
want anything at all ?
Please advise,
Ann R.
On Jun 9, 2017, at 1:07 PM, jeffrey E. <jeevacation®gmail.com> wrote:
Ask god for price timing. If I do not. One at all
On Fri, Jun 9, 2017 at 10:43 AM Richard Kahn < wrote:
Richard Kahn
Begin forwarded message:
From: Ann Rodriquez <
Subject: Ken Floyd: VI Paving
Date: June 9, 2017 at 12:07:49 PM EDT
To: Rich Kahn et >
Begin forwarded message:
From: Ken Floyd <[email protected]>
Date: June 9, 2017 at 11:28:41 AM AST
To: Ann Rodriquez
Cc: Jermaine Ruan
EFTA01043730
Subject: Re: LSJ MAP
Good Morning, Ann,
Please do not take offense at anything I am writing here, as you asked me to put down my issues in an email. Primarily, because
we could not have a correspondence call via phone.
It appears we are again at the same place, at a different time.
The only difference is the idea of, "Economy of scale", by holding out the possibility of doing GSG as a reason to give a lower
price.
The idea behind a better price due to increased quantities is logical; if the extra work is included in the schedule of values and
Schedule of work.
It appears the viability of the project hinges on the ability of the owner to maintain a location of privacy, a position of which I
respect and am totally committed.
However, requirements such as these do not mix well with expedition and even more important to me, quality.
In Civil work, especially involving a product such as asphalt, which needs to be protected from fast running water and standing
water in order to last, the underlying surface and water travel need to be addressed prior to application of the final surface
course. The roads on both Islands were not cut with that in mind and need some intense mitigation. From the formation of
retention ponds to swales and low-water crossings.
All of the items will be outlined and a unit cost applied to each activity, which will make any approved changes transparent
regarding cost. This will be in our,
Speed and Quality come together at a premium and I cannot put together a price based on Speed, Quality, Economy of Scale
and maintaining privacy for a project in a piecemeal fashion.
I take great pride in performing ow work in the best quality possible.
If we perform this work, it will be after an approved price and Project Schedule. In order to provide you with these items, I need
to know what issues I will be faced with and the issues which are not negotiable.
I have no idea of how often or how much notice is or can be provided regarding when privacy is necessary, but it would be
productive to stop work on one island while performing work on the one next door. This is just one proposal.
I am going to have to finish up due to other appointments.
I hope I did not give the impression I don't want to do your project. The opposite is the truth. Want to do an organized, clean
and quality job, nothing less.
Sincerely,
Ken Floyd
On Wed, Jun 7, 2017 at 2:47 PM, Ann Rodriquez < > wrote:
Hi Ken,
The owner would like to see the turn out of LSJ "Road Paving" before we proceed with GSJ
We would like to start LSJ asap. Can you please revisit your bid and give us the best deal possible as
we would also like to proceed with GSJ right after our LSJ paving project.
Please advise,
Ann R.
On Jun 7, 2017, at 12:33 PM, Ken Floyd < wrote:
Good Afternoon,
Both of these sketches are labeled LSG, which I take to mean they are not of GSG. Could I get a scale drawing of the Topo
for GSG?
Thank you very much,
Ken Floyd
On Wed, Jun 7, 2017 at 12:11 PM, Jermaine Ruan > wrote:
EFTA01043731
With Respect,
Kenneth Floyd, Virgin Islands Paving
General Manager, STT
With Respect,
Kenneth Floyd, Virgin Islands Paving
General Manager, STT
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01043732
ℹ️ Document Details
SHA-256
db7ac807b7cce9b89b9550c8c0e2abbfc40b41f2354e408e70635d7987f8e06a
Bates Number
EFTA01043730
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0