GSJ Tiki House
Scope of work:
Demo the following
1. Cabinets and Veneer Counter Tops
2. Existing Thatch
3. Manufacture Wood Flooring
Install new Hardwood Counter Tops ,High Gloss Finish, with bar sink and faucet.
Install New Roof Decking and Pick up points
Finish Ceiling in T&G Cedar.
Install Dura Rock Subfloor and Finish with Rustic Grey floor tile
Install New Cabinets
Refinish Bar Seat with Hardwood in a High Gloss Finish
Duration: 23 days, 2 Men
GSI Sea Water Intake Shed
Scope of Work:
Fabricate a 4' X 4' concrete base
Fabricate a 4' X 4' motor and pump cover to house new Sea Water Pump.
Piping and Electrical in house.
Duration: 2 Days, 2 Men
labor Cost
Brian: $300.00 per day @ 25 days = $7500.00
Buck: $120.00 per day @ $25 days = $3000.00
Total Labor Cost: $10,500.00
All material and tools supplied by Owner.
EFTA00802886
ℹ️ Document Details
SHA-256
e369557523aa87a67c3726a94845085b3de60b4b6a773fdd206a3782c2e0e4d1
Bates Number
EFTA00802886
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0