From: emad hann
Sent: Monday, May 16, 2011 9:27 PM
To: Gary Kemey
Cc: Jeffrey Epstein
Subject: Re:
Gary,
Other items that I have not seen you respond =o are (unless you responded to JE and did not include me on the e =ail)
Ion =chedule
Dock House
More People
Tile =ayer
Nursery Floor
Mooring
Fire Fuel =esalination Mechanical done by 4/17
Thank =ou
Emad Hanna
Project Controller
HBRK Associates
301 East 66th St
Suite 10F
New York NY 10065
Cell
LSJ Office
St. Thomas Office =
NY Office
Fax
On May 16, 2011, at 2:38 PM, Gary Kerney wrote:
schedule for the =th
Main pool
the building slab will =e poured and block going up
the pool equipment =ill be installed and water in pool
the retaining walls around cottage will be up
the deck will be concrete,ready to lay tile(tile comes =fter the building is stoned)
EFTA_R1_00112782
EFTA01788373
still on target for 10/3
Flag pole pool
the building will be framed in and plastering =nderway
the pool equipment will be in and water in the pool =assumes we get tile selection)
the deck will be concrete(tile happens after shelter =nd plaster)
walls will be underway
still on target for =/15
2
EFTA_R1_00112783
EFTA01788374
ℹ️ Document Details
SHA-256
e5621e2db87744fc99e47e258616c44597dc8f442bacbd0885b123ebdcb69d44
Bates Number
EFTA01788373
Dataset
DataSet-10
Type
document
Pages
2
💬 Comments 0