To: Emad Hanna
From: Jeffrey Epstein
Sent Mon 7/27/2009 4:18:54 PM
Subject: Re: Mechanical Building
gary has to decide it ok
On Mon, Jul 27, 2009 at 11:34 AM, Emad Hanna < wrote:
Jeffrey,
I just wanted you to be informed of the following:
Gary Kerney has approved a payment of $ 9,241 to Kraus Manning for testing on the
mechanical building.
This puts this budget line item over budget by $ 7,771 and Gary also stated there will be an
additional $ 12,009 of testing fees.
So he is adding a change order for $ 19,771 bringing the total amount for testing to $ 29,771.
If you're ok with all the above I will process this payment and adjust the working budget for
the change order.
Thank you
Emad Hanna
Project Controller
HBRK Associates
PO Box 400
EFTA_R1_00188984
EFTA01815765
New York, NY 10150
Ph
Fax
EFTA_R1_00186985
EFTA01815766
ℹ️ Document Details
SHA-256
edb0d164b74ba8ef8d1115bedd5f2064a04af9fd9403ff79a780b31459514b7a
Bates Number
EFTA01815765
Dataset
DataSet-10
Document Type
document
Pages
2
Comments 0