From: Richard Kahn
To: Jeffrey Epstein <[email protected]>
Subject: Fwd: Peter Elie - Pebble Beach Construction Project - February 1, 2019
Date: Fri, 01 Feb 2019 16:16:50 +0000
Attachments: Peter_Elien Pebble_Beach_Construction_Project_-_February_1,2019.pdf
Peter Elie bid for Pebble Beach labor only was as follows:
Foundation and Slab 7500
Columns 6500
Total Labor only 14,000
Please note we will pay for all materials
Peter is able to begin monday
please advise on scope of work, pricing and timing
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York NY 10022
tel
fax
ce
Begin forwarded message:
From: Daphne Wallace <1
Subject: Peter Elie - Pebble Beach Construction Project - February 1, 2019
Date: February 1, 2019 at 11:31:56 AM EST
To: Rich Kahn
Greetings Rich,
Attached please find the Materials list and Labor cost from Peter Elie for the Pebble Beach project.
I recommended, and Mr. Elie agreed that Mr. Elie call in the orders himself. That way if substitutions or
changes are needed or recommended by the vendor, he can address them immediately.
I will place Mr. Elie on the MSI account if you are in agreement with my recommendation. If he needs to
make a purchase from Home Depot, he can leave the items at the Pro Desk, and I can call in payment. The
same with Heavy Materials, he can call in the order, I will make the payment. That should insure there are no
errors with an order.
EFTA01028686
Mr. Elie received a Contractor's package from me today so that is also taken care of. I will scan and send to
you when I receive it back.
EFTA01028687
ℹ️ Document Details
SHA-256
f017efd7a64974b6bde9dc40444708a9a6379fc305753f8ecfa5394581b4b797
Bates Number
EFTA01028686
Dataset
DataSet-9
Type
document
Pages
2
💬 Comments 0