From: "Jeffrey E." <[email protected]>
To: "John P. Woods" •
Subject: Re: GSJ Permit
Date: Thu, 22 Dec 2016 21:19:00 +0000
ok
On Thu, Dec 22, 2016 at 3:44 PM, John P. Woods < wrote:
Good Day,
Attached is the draft letter I am sending with the drawings for GSJ. I am
also attaching the drawings for your review. It is my intention to submit
this package tomorrow before the VI Government closes at 1:00 p.m. Let me
know if there are any changes to make.
JPW
Original Message-----
From: John P. Woods [mailto:
Sent: Wednesday, December 21, 2016 10:14 PM
To: jeffrey E.
Cc: Darren Indyke; John P. Woods; Erika Kellerhals; Amy Dempsey
Subject: GSJ Permit
Good Evening,
I met with J.P. Oriol yesterday to discuss the drawings that we will be
submitting to in essence replace the unexecuted permit that will ultimately
serve as a "master plan" for the island. We discussed what needs to be
included in the drawings and I came away with the following points:
I. A helipad, by VI Code Title 29 Section 226, paragraph (h) requires a
helipad to be approved by DPNR, Public Works, VI Port Authority, and the VI
Legislature. It is my understanding we are not asking for a helipad, but a
concrete pad/terrace that may be used as a landing site. J.P. feels we
should apply for this site separately as it could hold up the rest of the
scope. What I feel we need to do is state clearly in the description of the
pad it is not a helipad. We should further state that in the future it may
be used as a landing site, at which time we will apply for all "necessary"
permits. Of course we don't believe any other special permit is required
other than a determination that a rook is not within 1000 feet of the site.
I strongly recommend Amy do that study now to make that determination.
2. Access on to the island is important to define now. J.P. seems to feel
the existing dock site should remain and supplement it with the dock across
from LSJ. He has concerns about the dock in Christmas Cove and the temporary
barge landing regarding their ability to withstand Winter swells on the
Western side of the island. He also feels the barge landing should be
incorporated into one of the dock sites as it is on LSJ. Amy has already
said the ACOE does not like the existing dock site, so that is out. The
marine facilities on the western side will need to evaluate wave activity
EFTA01058511
throughout the year to validate the western sites. We don't have to show
these access points at this stage, but they should be seriously considered
as it relates to where we are placing structures like storage and
maintenance sheds.
3. DPNR will likely stand by their interpretation of the height of the
flagpoles. We will need to apply for a variance from BLUA to try and get the
height waived. Erika, let's work on that. I think the basis should be the
inconsistency I referenced in my earlier correspondence to the Commissioner.
4. I have defined the work scope into two phases. The first phase deals with
cleanup, stabilization of existing driveways, landscaping, flagpoles,
concrete pads, and new driveways. Phase 2 consists of structures such as
residential cottages, pools, and storage buildings. We are doing that
separation because we don't have enough definition on the buildings to get
them fully permitted. We would also need complete plans, elevations, and
sections. We can, however, get them approved conceptually with special
conditions that will require us to submit more complete drawings when we are
ready to construct those buildings.
5. We can request this new scope replace the scope of the unexecuted permit.
This will save a lot of time, if they accept it. The inclusion of new
driveways will be the impetus to request modifying the limitations on types
of equipment that can be used.
I intend to make the submission over the next days, depending upon the VI
Gov. holiday schedule. Once approved, modifications and additions to the
scope will be easier to receive and take less time than acquiring multiple
CZM permits.
JPW
Sent from my iPhone=
This email has been checked for viruses by Avast antivirus software.
https://www.avast.com/antivirus
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
EFTA01058512
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01058513
ℹ️ Document Details
SHA-256
f3b34ce138ec87c99f12d306eb777e17a913640dae7f5a367d78bb23b5c0c109
Bates Number
EFTA01058511
Dataset
DataSet-9
Type
document
Pages
3
💬 Comments 0