From: Daphne Wallace
To: Jeffrey Epstein <[email protected]>
Cc: ann rodriquez , Rich Kahn
Subject: Dome progress - January 23, 2014
Date: Thu, 23 Jan 2014 14:37:46 +0000
Attachments: Dome_(1)_-_Jan_23,2014.JPG; Dome_(2)_-_Jan_23„2014.JPG
Greetings Mr. Epstein,
Attached for your review and comments are dome progress photos. Also for your review is the schedule for the
dome completion and installation:
Skin of dome will be 75% completed by 1/24, 100% completed by 1/27.
Spray painting and sealing of skin to begin 1/27, 100% complete by 2/3.
Will dismantle dome for transportation by 2/5
Big N and flatbed will pick up dome on St. John 2/6 or 2/7.
Samson crew will reassemble dome on LSJ 2/7 or 2/8.
Samson crew and LSJ boom lift will install on roof of Five Palms by 2/10.
Final paint touches can be completed on installed dome 2/11 or 2/12.
Respectfully submitted,
Daphne
EFTA00651281
ℹ️ Document Details
SHA-256
fa6d04ffe367f683bd7c88ba143f685d7ff625f9d215af973cb07a8c5858b4c1
Bates Number
EFTA00651281
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0