📄 Extracted Text (149 words)
St. Thomas, VI 00803 Date: May 27, 2016
Tel: Re: Project Cancellation
Costs
To: WE LLC Project: Asphalt Paving
Attn: Rich Kahn Little Si James Island
Dear Mr. Kahn,
Please see the project cancellation costs below;
• Work Performed
o 45 trucks materials hauling @ $400.00 per $18,000.00
o 884 tons agg. base loading and spreading 2,652.00
o 884 tons agg. base structural compaction 4 420.00
Subtotal $25,072.00
Overhead 15% $3,760.80
Total $28,832.80
• Mobilization Costs (3 times)
o Personnel — 96 man hours @ $45.00 per $4,320.00
o Equipment Transportation — 21 @ $350.00 per 7,350.00
o Specialty Equipment shipping, taxes, clearing 4 120.00
Total $15,790.00
• De-mobilization Costs (3 times)
o Personnel — 96 man hours @ $45.00 per $4,320.00
o Equipment Transportation — 21 @ $350.00 per 7.350.00
Total $11,670.00
• Cancellation Costs 15% $512,500.00 $76,875.00
Total Costs $133,167.80
1
Project Cancellation Costs
LSJE LLC
EFTA00593657
ℹ️ Document Details
SHA-256
faf87530b8f20d6a8c20300b8b44d269f9bd743737d4b627a4c870d141c613dd
Bates Number
EFTA00593657
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0