Zorro Projects - 7/12/13
Landscaping (22) - Start End Total Est. Cost ' Notes Photo
Rear Planter Bed 6/1/13 $75,000.00 3/28/13 - Refurbishment & Maintenance proposals from 3
Front & Rear Parking Beds companies forwarded to RK & DI
Bowel Garden 4/27/13 - JE approved Aspen Landscaping for Refurbishment
Aspen Grove 5/9/13 - New proposal forwarded to JE & RK, awaiting direction
Pinion Screen 5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next week
6/18/13 - More plant material arrived
6/21/13 - Planting & Irrigation complete at back parking area.
6/22/13 - Planting & Irrigation continues around chess set -
attached photos
6/26/13 - More plant material arrived on site
6/27/13 - Preparation front parking area begins, Columbians &
Trumpet Vine planted along pathway between MH & Dog Pen.
Irrigation installed in all planted areas - attached photos
7/12/13 - Plant & Irrigation installation continues, attached plant
schedule & photos
Landscape Light Timers Replacement - Start End Total Est. Cost Notes Photo
4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal
7/12/13 - Have requested revisions to proposal, updated proposal
due 7/14/13
EFTA01124666
Zorro Projects - 7/12/13
Landscaping - In House - Start End Total Est. Cost Notes Photo
Ponderosa Pines at Front Entrance & 6/3/13 4/27/13 - JE approved the removal of dead pine in courtyard &
Landscape Lights at MH Ponderosa Pines, Landscape Lights & relocate Pinions to the area.
6/3/13 - Project Started
6/7/13 & 6/18/13 - Removal of Ponderosas & Pine complete
6/25/13 - Work to begin on landscape lighting
6/29/13 - Have installed landscape lighting where planting is
complete, will continue next week
7/12/13 - Continue installation of lighting . as planting is
completed
Terraces (27) - Three B's Start End Total Est. Cost Notes Photo
Terraces - $52,000.00 4/7/13 7/3/13 $56,200.00 12/12/12 - Bid Received
Stucco/Gutters/Painting - 54,200.00 3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached photos
6/18/13 - Stucco & Painting scheduled to start
6/21/13 - Stucco & Painting Complete - attached photos
6/24/13 - Final review of completed work
7/2/13 - Final Punch Out to begin of all outstanding work
7/3/13 - Project Complete
EFTA01124667
Zorro Projects - 7/12/13
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes Photo
$10,125.00 + 4/20/13 - Bid received, requested vendor to make adjustments
tax 5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend.
6/8/13 - Final bid attached, also forwarded separately to RK.
6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
6/19/13 - Resubmitted revised pricing to RK - awaiting direction
6/28/13 - RK requested that Three Ws submit an estimate for this
work. Have contacted Three B's, will be on site next week to
review
7/11/12 - Three Ws bid approved. Request for depoist of
$6,750.00 forwarded to BK & RK, awaiting date to begin work
Cooling Tower (36) - JBH Start End Total Est. Cost Notes Photo
7/8/13 4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/20/13 - Unit on site - attached photo
6/21/13 - Noting attached E Mail, JBH have pulled their team off
moving forward with this project until RK makes contact about
outstanding balance
Payment received by Vendor
7/8/13 - Project begins
7/12/13 - Attached photos
7/17/13 - Completion expected
EFTA01124668
Zorro Projects - 7/12/13
Replacement of Pool Pac (33) - Start End Total Est. Cost Notes Photo
Engineering Inspection - $9,100.00 9/11/12 4/29/13 - Quote forwarded to RK, who requested more detail
Unit Cost - $43,170.00 5/8/13 - Revised quote forwarded to RK, awaiting direction
Camera Ducting Inspection - $1,214.91 5/22/13 - Beaudin Ganze on site to review project
Ducting - TBA 5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 -JE approved investigation via camera.
6/3/13 -JBH forwarded estimate
6/4/13 -JE approved moving ahead
6/11/13 -JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiting
report/disc.
6/21/13 • Report/Disc forwarded to Beaudin Ganze, awaiting
report
7/8/13 - Report due
7/9/13 - Informed that report has been delayed
7/12/13 - Report due 7/18/13
Repair Pool/Spa (29) - Start End Total Est. Cost Notes Photo
$12,600.00 5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
JE requested work be completed In Sept
_
Water Sample of Tap Water- Start End Total Est. Cost Notes Photo
6/12/13 7/3/13 $1,391.00 4/27/13 - JE requested water samples be taken.
This will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/2/13 - All Wells up and running
6/12/13 - Water samples taken. Results due back 7/3/13
7/3/13 - Results, forwarded to JE 7/11/13
EFTA01124669
Zorro Projects - 7/12/13
Exterior Doors Main House - Three B's Start End Total Est. Cost Notes Photo
7/2/13 7/9/13 4/27/13 - JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
7/2/13 - Final Punch Out to begin of all outstanding work
7/9/13 - Project Complete
Audio Upgrade - In House Start End Total Est. Cost Notes Photo
New TV's 6/3/13 7/6/13 Installed - final programming required
DVD Players/Theater Upgrade Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward
5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm, Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Marantz DVD in
Breakfast Rm
6/22/13 - Awaiting delivery of Marantz DVD
6/27/13 - Unit has shipped
7/5/13 - Installation & Programming complete
7/6/13 - Project Complete
Kitchen Table Electrical - (35) - Three B's Start End Total Est. Cost Notes Photo
Electrical & Data Cut In - S2,160.00 6/3/13 3/1/13 - Bid received Lead Time 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/13
6/13/13 - Conduit installed, tiles replaced & grouted. Cat 5 still to
be pulled and punched down
EFTA01124670
Zorro Projects - 7/12/13
Media Room Curtains (24) - Start End Total Est. Cost Notes Photo
Blackout & Rings 2/24/13 $6,262.08 4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) - BO End Total Est. Cost Notes Photo
lined & Rings 2/24/13 $2,527.01 4/27/13 -JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwards to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Gym - Mirrored Doors - Three Bs Stare End Total Est. Cost Notes Photo
2/24/13 7/8/13 3/4/13 - Project Complete. JE requested further work, which will
begin once Project 27 - Terraces complete
7/2/13 - Final Punch Out to begin of all outstanding work
7/8/13 - Project Complete
Phones Main House 131) - &in End Total Est. Cost Notes Photo
4/27/13 - JE approved installation of new phones at MH
Awaiting for service provision & estimated cost of delivery of
services - Project 21Microwave & IT
6/22/13 - Awaiting response from Southwestern Wireless on FCC
License Application & Router at MH
6/28/13 - Requested RK to forward deposit
7/17/13 - Installation to begin
Phones Ranch Central (35) - Start End Total Est. Cost Notes Photo
6/21/13 - Will forward proposal for phone system by 6/28/13
6/27/13 - Project On Hold until Microwave solution resolved
EFTA01124671
Zorro Projects - 7/12/13
Microwave & IT - (21)- Start End Total Est. Cost Notes Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses 0 Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery of Services
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confirming
details before forwarding
6/15/13 - Informed JE, will forward once all details confirmed
6/20/13 -JE approved South Western Wireless bid. RK to
negotiate final bid
6/27/13 - Southwestern Wireless unable to delivery bundled Ti
6/28/13 - Looking Into options
7/12/13 - Awaiting proposal from Advanced Communication,
expected 7/19/13
Cell Repeaters & WI-Fl - In House Start End Total Est. Cost Notes Photo
Cell Repeater - Library 7/3/13 7/8/13 7/8/13 - Project Complete
Cell Repeater - Gym 7/3/13 7/8/13 7/8/13 - Project Complete
Computers - Start End Total Est. Cost Notes Photo
Lap Top - Lodge Requesting Approval to Purchase
Desk Top - RC Office Requesting Approval to Purchase
Well K (37)- Start End Total Est. Cost Notes Photo
Plugging First Hole $15,000.00 Estimate to plug in hole
- — —
EFTA01124672
Zorro Projects - 7/12/13
Lodge Roof Start End Total Est. Cost Notes Photo
Repair/Replace Broken Sections Three B's will complete after summer visit
Yurt - (23)- Start End Total Est. Cost Notes Photo
Replacement Walls/Roof/Door/Windows 5/9/13 $6,355.00 4/27/13 -JE approved investigating options
plus shipping 5/9/13 - Project Request forwarded to RK & JE
charges of 5/9/13 -JE approved Project, awaiting direction on deposit
approx. payment from RK
$480.00 (COD) 5/13/13 - Deposit forwarded to vendor - $3,177.50
Removal of furniture, deconstruction of existing
walls/roof/windows & door. Then reconstruction of base,
resanding/sealing floor required - In house
7/5/13 - Balance paid - $3,177.50
7/9/13 - Shipped from vendor
7/15/13 - Due on site
Repair/Painting Work - Ion - (34) Start End Total Est. Cost Notes Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work that
will be required after MBR Terrace is completed.
6/29/13 - Additional work - Sign on Adobeeffice Wall
Septic System -Adobe (38) Start End Total Est. Cost Notes Photo
7/10/13 7/9/13 - E Mail forwarded to RK - Adobe septic is blocked ZDC
unable to clear line.
7/10/13 - Bassett Construction on site to review system, inspect
lines with camera. Found compressed line under the Adobe
outside deck. X
7/11/13 - ZDC will remove pavers after visit, Bassett Construction
will complete repair & ZDC will reconstruct deck area - attached
photos
EFTA01124673
Zorro Projects - 7/12/13
Painting/Staining/Sealing-In House Start End Total Est. Cost Notes Photo
Stables - including outside/inside lights 7/8/13 - Inside/Outside Lights complete.
7/9/13 - Work to begin after visit on the outside.
7/12/13 - inside resurfacing, painting/staining to be completed
over the Winter
Adobe - including wooden deck & front Work to begin after the visit
Log Cabin Work to begin once all painting/staining projects complete at RC
Lodge Work to begin once all painting/staining projects complete at RC
Reservoir Work be begin once all painting/staining/sealing projects complete
Fuel Storage Tanks Work to begin once all painting/staining/sealing projects complete
RC Office Interior Work scheduled for Winter
RC Mechanical Bays & Garages - interiors Work scheduled for Winter
Dead Tree/Branch Removal - In House Start End Total Est. Cost Notes Photo
7/11/13 NA 7/11/13 - Removal of Dead Tree/Branches in Adobe yard begins -
attached photos X
Fuel Storage Tank Area - In House Start End Total Est. Cost Notes Photo
Removal of grass. Matting & edging to be
installed
Gravel/Edge Work RC Paths - In House Start End Total Ed. Cost Notes
All paths to be dug out, edged and gravel Photo
to be installed
Log Cabin Start End Total Est Cost Notes Photo
Step Outside - Repair/Replace Broken 7/12/13 7/12/13 - Section removed, new section to be refabricated
Section
EFTA01124674
Zorro Projects - 7/12/13
Caboose - In House Start End Total EA. Cost Notes Photo
Installation of Retaining Wall To begin early Fall
4 Bay Garages - in House Start End Total Est. Cost Notes Photo
Repair Leaking Roof To begin early Fall
Repair Damaged Wall To begin early Fall
Pole Barn Water Truck Parking Start End Total Est. Cost Notes Photo
Installation of a Retaining Wall To begin late Fall, Early winter
Cattle Gates/Guards x 3 - in House Start End Total Est. Cost Notes Photo
Refurbishment, Empty & Paint To begin early Fall
Cactus Removal - In House Start End Total Est. Cost Notes Photo
To begin late Fall, early Winter
Tilt Trailer - In House Start End Total Est. Cost Notes Photo
Refurbish/Paint Winter Project
Vehicles Start End Total Est. Cost Notes Photo
2013 Ford Expedition - review Captain 3/27/13 5/2/13 - Estimate received -$11,528.74
Seats to be installed 5/31/13 - as of date unable to get a 2nd estimate,
Start End Total Est. Cost Notes Photo
4/27/13 - JE approved investigating purchase of 2 dogs.
Researching
EFTA01124675
Zorro Projects - 7/12/13
Inventory/Clean Work Shoos - In House Start End Total Est. Cost Notes Photo
6/6/13 6/20/13 - Landscaping, Paint & Wash Bay 90% complete -
attached photos. All these location will be painted over the winter
6/21/13 - Work continues as time allows - complete clean up &
inventory of all work shops at RC & MH
6/29/13 - Landscaping, Paint, Irrigation & Wash Bay 95%
complete, but all require painting over the Winter. Welding, X
Woodshop, Mech Shop 80% complete
7/12/13 - All RC Workshops 95% complete, painting &
table/bench resurfacing to be completed over the winter -
attached photos
Purchases Start End Total Est. Cost Note Photo
Outside Pool Furniture Investigating Options
Pool Pace Clock 4/25/13 7/9/13 7/10/13 - Due on site
7/9/13 - Unit on site, complete
Facial Machine to purchase
Wells - Dakota & K
Combined Usage as of date 7/12/13 10.18 aft
2014 Budget
Bunkhouse Start End Total Est. Cost Notes Photo
Window/Doors - Total Replacement
EFTA01124676
ℹ️ Document Details
SHA-256
fbd6a19066c76a72727f05c4772d1bfdd9728711037f3b08561e1ff9dd953c1c
Bates Number
EFTA01124666
Dataset
DataSet-9
Document Type
document
Pages
11
Comments 0