MASTER
1. Walls and ceiling painted.
2. Floor leveler applied.
3. Floor underlayment down prepared for wood flooring.
4. Thassos going on walls
S. Coral laid up to shower, patched around columns
COTTAGES
1. Roofs painted
2. Cabinets set tops on
3. Ion painting walls
4. Doors and shutters complete on
5. Baths complete
I in progress on 1&2
6. Ac operational
KITCHEN
1. Walls standing
2. Roof framing starting
LAUNDRY
1. Forms stripped
2. Stairs formed and poured.
3. Stone veneer S0% done
4. New road at grade for approval
S. Jeffrey drive walls mocked up for approval.
6. Interior walls being plastered.
6 k4 42
W I
p t\o et'6
EFTA00600290
LLCI. LIVILWOPIP•a
1. Generators in place
2. Switch gear in place
3. Fuel piping underway
4. Fire system complete
DESAL BUILDING
1. Backfill continuing
2. Second storey wall standing
3. Top slab Ya formed
LIBRARY
1. Remove furniture/francilli working
BEACH
1. Deck poured ready for tile
EFTA00600291
ℹ️ Document Details
SHA-256
fd1292cfdb219c14b5cacaac3bf308f0fcfdec9fff52f9c7f1ce6b5a89023563
Bates Number
EFTA00600290
Dataset
DataSet-9
Type
document
Pages
2
💬 Comments 0