DARREN K. INDYKE
New York, New York 10022
Telephon
Te'maple
Email:
July 20, 2018
VIA Email --
Mr. Brian Walden
Director of Operations
ProSolar America, LLC
Dear Mr. Walden:
I am general counsel to Great St. Jim, LLC and LSJE, LLC ("GSJ"), which own and operate
Great St. James Island in the U.S. Virgin Islands.
I understand that GSJ purchased a 310.8 kWh solar power system from ProSolar Systems,
LLC ("ProSolar") in November 2016 for a purchase price of $192,211. Included as part of that
purchase were 12 self-contained Acquion Maintenance Free Salt Water Battery Modules for an
aggregate price of $154,338, each being sold with a 3-year warranty from ProSolar, which will
not expire before November 2019. I also understand that GSJ has also been paying ProSolar in
the amount of $350 per month for monthly maintenance/service calls which have been taking
place since April 2017 and that after Hurricanes Irma and Maria hit the U.S Virgin Islands in
September 2017, GSJ paid in excess of $111,000 to troubleshoot and bring the solar power
system into full operation.
Despite the purchase of a specially designed solar power system that was to provide Great
St. James Island with continuous power to meet its energy demands (which GSJ fully disclosed in
advance to ProSolar) without interruption on a full-time basis, and was warranted for three years,
the power system has been failing regularly, shutting down like clockwork every morning at
approximately SAM. This then required GSJ's representative to travel to the island to turn off
island-wide power drawing from the system, so that the system could recharge. Once the system
recharged, it then had to reboot completely before GSJ's representative was able to reconnect
power to Great St. James. Obviously, this was not what was proposed by ProSolar, not what was
agreed to and certainly not what GSJ paid almost $200,000 for ProSolar to deliver. Moreover,
after more than year of paid monthly service calls and an additional $111,000 of replacement
and repair work to bring the solar power system into full operation over the past several months,
and despite ProSolar's knowledge of the existing conditions on Great St. James Island and
continued reports to ProSolar of increasingly regular low voltage system failures, only recently
EFTA00799455
Mr. Brian Walden
Director of Operations
July 20, 2018
Page 2 of 3
did ProSolar tech personnel open the battery modules to examine the circuit boards contained
therein. ProSolar advised that only after it examined these circuit boards which supply the
charging and discharging controls for each battery module did it discover that several were
corroded. It now believes that this is the source of the problems with the system.
Two weeks ago, ProSolar attempted to implement what it maintains is a solution to the
recurring problems experienced on Great St. James. The solution was to effectively bypass the
circuit boards, and in the process, eliminate whatever functionality they should have provided
had they been functioning properly. Although a full assessment needs to be completed
concerning the extent to which the work recently performed by Pro Solar's technicians has
improved the system's wholesale performance failures, improvement will not resolve the issue
or satisfy ProSolar's contractual obligations to GSJ. A system that does not fail quite as often as
it used to is no substitute for a fully operational, properly programmed and integrated solar
battery system that functions as specified and has no defects in its design, circuit boards,
programming, control systems, or otherwise. GSJ paid ProSolar in full for, and ProSolar is
obligated to provide to GSJ nothing less than, a solar power system with the full functionality you
contracted to deliver and warranted for three years. Moreover, the three-year warranty that GSJ
paid for has no value at all if replacement parts for the system cease to be available during the
warranty period, which is what now appears to be the case.
Nor is it reasonable to blame your contractual breaches on damaged circuit boards in the
solar batteries that you claim are the result of environmental conditions on Great St. James
created by Hurricanes Irma and Maria. ProSolar has made regular service calls to Great St. James
after the Hurricanes hit the Island, for which it was paid in each instance by GSJ. It was well aware
of those conditions on Great St. James, but never once during any of the numerous service visits
it made to Great St. James after September 2017 did ProSolar examine the circuit boards. Thus,
if indeed the damaged circuit boards played a role in the system failures, ProSolar's own gross
negligence in servicing the solar battery system eliminated any possibility of early detection or
damage prevention. It was only after GSJ complained of the continuous, regular system failures
and only after numerous on site visits that ProSolar then finally examined the circuit boards. But
by then, the damage was done, and now no replacement boards are available.
Moreover, it is our understanding that the system was never properly programmed and
integrated and there have always been incompatibility issues with respect to the circuit boards
which ProSolar blames for the system failures. This defect in ProSolar's design of the integrated
system it contracted to deliver was a problem from the very beginning that was never resolved.
Once again, this is not what GSJ paid for and not what ProSolar contracted to deliver and
warranted to GSJ.
EFTA00799456
Mr. Brian Walden
Director of Operations
July 20, 2018
Page 3 of 3
ProSolar must take full responsibility for its defective and non-conforming system and
provide GSJ with the system that actually functions and performs as agreed, including as
necessary, by replacing the battery system in its entirety. Otherwise, ProSolar must provide GSJ
with a full refund of all amounts paid to ProSolar in connection with the system, including,
without limitation, the $192,211 paid for the system, the $111,000 paid to bring the system into
operation and the $350 per month of ProSolar's service calls that never properly diagnosed or
fixed the system's problems.
Please coordinate with Mr. Richard Kahn to advise how you will fully and properly resolve
ProSolar's contractual breaches.
This letter is without prejudice to the rights and claims of GSJ against ProSolar, including,
without limitation, the right to bring legal action against ProSolar to recover all amounts incurred
by GSJ in connection with the defective and non-conforming solar power system delivered by
ProSolar, consequential damages and attorneys fees and costs, all of which rights and claims are
hereby expressly reserved.
Very truly yours,
/s/ Darren K. Indyke
Darren K. Indyke
EFTA00799457
ℹ️ Document Details
SHA-256
0876495944db1f12fa518becb1ebaff752b4fc39e04bc09524fde325e7a81191
Bates Number
EFTA00799455
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0