LSJ Cistern Repair Estimate
Crew Average
Cost! Material Labor Crew Labor Subcontractor!E
Description of Operation OW Unit Unit Cost Hours Rate Cost quipment Rental Total
Cistern # 1 1 ea S1,080 62 $35 $2,170 $150 $3,400
Cistern # 2 1 ea S900 62 $35 $2.170 $150 $3,220
Cistern # 3 1 ea $480 42 $35 $1,470 $150 $2,100
Cistern # 1 outside wall coating &
repair 1 ea $350 24 S35 5840 _S1.190
L
Allowance for crack repair after
cisterns are drained & inspected:
# 1 Is leaking and will be repaired
with hydraulic cement before
coating 1 $350 24 $35 $840 $840
g
Material delivery to Red Hook 1 ton $250 $250 $250
SUBTOTAL $11,000
20% OVERHEAD AND PROFIT 2.200
TOTAL 13,200
(1) Assumes all cisterns are fully d ained by onsite crew
(2) Assumes onsite trash disposal
(3) Assumes all transportation supplied by LSJ
(4) This quote is good for 30 days
(5) Upon Notice to Proceed, 100% material & 50% labor deposit required.
(6) Balance due upon completion.
ℹ️ Document Details
SHA-256
183a3a6e70ca81d4bba43b5d9d0d440202e785ac668979a6f753dab19ff5184b
Bates Number
EFTA01109768
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0