EFTA01109769.pdf
📄 Extracted Text (152 words)
Outside Labor Budget # days Cost Per Day
5 Workers/Day
Site Prep 3 $3,000.00
Surveying/Layout/Raise Well
Cement Wall Elec Vault/Raise Well
Form Layout/Construction 3 $3,000.00
Rebar/Wire Mesh Installation 3 $3,000.00
Concrete Pour/Finish Work 4 $4,000.00
Concrete Protection/Pour/Remove 2 $2,000.00
Forms
Total Working Days is $15,000.00
Estimated Labor Budget:
Total of 5 extra men neeeded: this is outside labor/rehire. Our crew will be working on g
Repair of cement plan; excavation of soil needed to raise pad 4";etc
On pour days we will need a total of 10 pp; 5 will come from permanent staff
15 working days per outside worker X $200 per day per worker X 5 workers =
Note; We will know exact hires this week and determine their rate of pay based on who'
Have got paid in the past. We can determine a more exact work schedule after we know
workers speciality/talent.
EFTA01109769
rading
$15,000
they
each
EFTA01109770
ℹ️ Document Details
SHA-256
f9201333439250b8f83350ccd7f3372be2aafba278cffa437c1eec3b65511a53
Bates Number
EFTA01109769
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0