FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
PARIS
STATUS ITEM COMMENT
+ Update 1. Change fat lady painting frame i) 13/12 — Complete. See attached picture.
+ Update 2. AC in master bedroom — JE ii) 13/12 — Diffusers need to be changed. The diffusers need
says AC is broken — a/c cuts off to be specifically made and Serge will be contacting GM
after 30 mins. wk of 16 Dec to discuss this.
+ Update 3. Safe iii) 13/12 — Further delayed from 18 Nov — expecting to
install by mid-Dec — scheduled for 16 Dec at 15h00.
+ Update 4. Raise globe desk iv) 13/12 — Complete.
+ Update 5. First aid v) 13/12 — Trauma / oxygen kit — Valdson has tried various
places to have oxygen tank filled and has been advised
that this is not possible in France. GM advised that she
will speak with her aunt at the hospital and have Valdson
take her the tank to be filled.
+ NC 6. Door Codes Changed vi) 13/12 — Complete
+ Update 7. Computers vii) 13/12 — Valdson installed second card reader on GM
computer and is now working.
+ Update 8. Photos for Apt viii) 13/12 - Nine 8% x 13 JE brain picture for dining room to
replace African heads — Valdson has pictures and will
1
EFTA00577661
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
hang these by 20 Dec.
ix) 13/12 - Three 714
/ x 1014/ JE brain picture — Valdson has
pictures and will hang these by 20 Dec.
+ JE to advise 12/12 - No pictures chosen for the Indian heads round
end of the living room — advised that JE still needs
to choose pictures.
+ Update 9. Paint Boudoir walls and loo + 13/12 — Fax sent to Jean on 3rd Dec advising that the
change carpet paint should be more pastel and the shapes should be
more subtle. Carpet will be changed after painting
complete. Valdson advises painter had a look at the
boudoir and will put forward a proposal. Pinto's office
have not yet received the new samples. Expect proposal
16th / 17th Dec.
► NC 10.AC in Kitchen xii) 13/12 - To be reviewed at the time as the AC in the new
apt.
Update 11.New Lampshade for lamp on JE xiii) 13/12 - Jean purchasing a new lampshade. Jean advised
desk. GM that this will be complete by 20 Dec.
Update 12. Bull Painting xiv) 13/12 — Valdson has removed painting and placed in
storage.
2
EFTA00577662
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
> Update 13. Pictures to Replace Bull xv) 13/12 — Valdson has hung the 5 frames where the bull
4 Painting painting was and sent GM a picture. See attached picture
+ Update 14. Pictures in guest corridor to be xvi) 13/12 — This is complete minus 2 that broke. Valdson
reframes w/pics on site has hung the pictures.
+ NC 15. Dining Collection xvii) 13/12 — JE previously advised that we were to utilize
own collection — plse advise what you would like us to
+ JE plse advise use.
+ Update 16. LSJ Model xviii) 13/12 — Has been shipped and expect to arrive at LSJ
end-Jan 2003.
3
EFTA00577663
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
NEW PARIS APT
STATUS ITEM COMMENT
> NC 20. JE wants schedule for work — i) 13/12 — JE received renderings and plans from Pinto's
inc layout, construction and office 7 Dec. Jean advised that the apt will be ready in 1
decoration year as agreed with JE. Updated plans have been
received by JE today 13 Dec.
+ Update 21. Change Windows before ii) 13/12 - Quote has been approved and expected
Winter completion is beginning Jan 2003 - this now will change
due to additional papers required.
iii) 13/12 — Last night, Darren received from Marie-Joseph
Experton a form of letter to be sent by the architect to the
building manager of 22 Avenue Foch. According to
Marie-Joseph, it is necessary for the manager of the
condominium to confirm in writing the condominium's
consent to the proposed windows change; the letter, to be
signed by Serge Boquet on behalf of SCIJEP, the owner
of Jeffrey's apartments, simply requests the necessary
consent from the building manager. Darren approved the
form of the letter and sent it back to Serge Boquet today,
along with two original powers of attorney from Jeffrey,
as manager of SCIJEP, authorizing Pinto's firm and
Gerp Architects to act on behalf of SCIJEP in connection
with obtaining any municipal approvals or building
approvals required for the window changes.
4
EFTA00577664
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
Pinto's office requested that Marie-Joseph contact the
lawyer of the owner of the apartment on the P' floor
below Nassif's apartment. Apparently, Pinto and Marie-
Joseph have been unable after repeated attempts, to reach
the owner. Marie-Joseph advises that although she has
made several telephone calls to the owner's lawyer, she
has still received no response. Marie-Joseph promised to
continue to follow up.
5
EFTA00577665
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
PALM BEACH
STATUS ITEM COMMENT
+ Plse advise 1. Stone Dock Steps i) 13/12 — JE advised he had drawn up a plan of how stone
steps should be done. Nick has tried to obtain a copy but
+ Update no-one can supply it. Can JE plse supply Nick with
sketch. Same stone as surrounds pool to be utilized for
this project as per JE.
+ Update 2. Repaint of House ii) 13/12 — First quotation to repaint interior = $24,250.00
+ JE plse advise iii) 13/12 — NS spoke with Charles Miller, and he
unfortunately does not know anyone. GM advised she
would contact some of her friends to see what
recommendations they have. GM has managed to come
up with one number only.
Nicole is also investigating some painters.
> 3. Re-Carpet iv) 13/12 — Blue carpet chosen by JE (9D200-27505 Silo
Inasquette 28S). Carpet company has been to the house
to measure and will supply quote by 18 Dec. This will
replace all the yellow carpet with the blue spots
(stairways, passages upstairs, guest rooms & passage
outside master room).
[ t; I L I LI 4. John Alessi v) 13/12 — Complete - $200.00 has been deducted.
6
EFTA00577666
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
• Update 5. Landscape Lighting vi) 13/12 — JE advised Patrick to install uplight garden
spotlights to make the garden appear more natural.
Patrick has installed 12 and is presently repairing all the
old lights & will be doing a master plan for all outside
lighting and where their switches are located.
Update 6. Installation of DSL line on GM vii) 13/12 — Marc is setting up technician to install line —
old computer scheduled 16 Dec.
Update 7. Purchase of colour cartridges viii) 13/12 — Patrick has replaced the cartridges in GM's
for GM's printer computer and has purchased additional stock. Stored in
stationery cupboard.
► Update 8. Wax Treatment on Wooden i. 13/12 — Quote received of $2,746.25 for one coat & to
Floors skim the floor, and for a second coat an additional
$2,198.00. This is for a clear gloss finish = $4,944.25. A
semi-gloss and satin finish can also be done. See
attached quote. This company was suggested through
Nicole.
► Update 9. Plumbing for Repair of Pink . 13/12 — the plumber has advised he is unable to repair as
Room this is a building problem, and contractor has come
around and will be quoting for the repair. Quote
expected 16 Dec.
7
EFTA00577667
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
ON HOLD
vii) NC 10. Auto Hurricane Shutters for xiii) JE sd not to do anything at this time with the shutters.
Remaining Sections of House
REDECORATION OF HOUSE
+ NC 11. Schedule from Pinto xiii) 13/12 — Pinto's office has still not supplied an update
despite calls and faxes sent.
8
EFTA00577668
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
457 MADISON
STATUS ITEM COMMENT
+ NC 1. Decorator for JE office i) Bastion supplied JE with info on proposed concept, and
JE is considering proposal.
+ NC 2. Darren's Office to buy new ii) JE wanted new furniture. GM to purchase new desk &
furniture cabinets for Lauren's area & conference table & look at
dividing unit for Lauren & Darren.
+ NC iii) JE liked image of furniture - catalogue of the furniture
+ JE to advise how and additional catalogues Edwina sourced given to JE.
to proceed
+ Update 3. Directory Update iv) 13/12 — All envelopes have been mailed that had
complete addresses. We are already receiving responses
and the records are being updated as received.
9
EFTA00577669
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
301 EAST 66TH
STATUS ITEM COMMENT
Update I. ION i) 13/12 — Carpet will only be installed week of 16 Dec as
arrived late from manufacturer.
ii) 13/12 — Edwina will personally work at the apartment 18
Dec to sort it out.
iii) 13/12 — Living room furniture is being delivered 18 Dec.
iv) 13/12 — Larry V is ordering TV and Hi-fi for delivery.
v) 13/12 — 2 telephone lines will be installed. Management
need to disconnect line as previous tenant has still not
disconnected, before the lines can be installed. Edwina will
Andrew attend to this week of 16 Dec.
10
EFTA00577670
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
65TH STREET
STATUS ITEM COMMENT
+ Update 1. AC in downstairs office i) 13/12 - Brian to polly fill edge of vent 16 Dec..
+ Update 2. Wireless in the basement for ii) 13/12 — Pat Callaghan installing 17 Dec when attending to
staff other work at 651h.
+ Update 3. Canvass to replace Kline iii) 13/12 — New canvas being ordered once GM chooses
correct size. Edwina to send GM email showing masking
tape of size on wall for GM to choose — attending to this
on 16 Dec.
+ Update 4. Strip Lights — Gym iv) 13/12 — Richard is ordering some parts needed for the
electricity supply — expected completion 23 Dec.
+ Update 5. Credenza v) 13/12 — The legs are being raised and will be returned 16
Dec.
+ NC 6. Carpet Cleaning vi) 13/12 — Scheduled for 17 Dec — living room, dining,
bedroom & GM office.
+ Update 7. Stick Hi-fi Wires vii) 13/12 — Brian will attend to complete this 16 Dec. These
need to be stuck down out of the way of the heat from the
fireplace.
+ Update 8. Hang Frames in the Gym viii) 13/12 — Brian will attend to this 16 Dec.
11
EFTA00577671
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
+ Update 9. Extractor in the basement & ix) 13/12 - Custom made extractor in the basement needed.
the main kitchen Rich is obtaining a quote. Expert viewed basement 11
Dec and expect quote by 20 Dec.
+ NC x) 13/12 - Extractor in the main kitchen — Rich looking how
to boost system + change filters and clean system which
should improve problem.
+ Update 10. Book shelves for photobooks xi) 13/12 — Brian will complete this 16 Dec
in the office
+ Update 11. Answer machine on the guest xii) 13/12 — Pat Callaghan installing in blue room &
line connecting to system 17 Dec when attending to other
work at 65'h.
+ Update 12. Suburban xiii) 13/12 — Car went in for full service as security system
was malfunctioning. It was discovered that the system
was perfect and working well, and that a third key had
been cut which was not factory issue causing the security
system to activate cutting the ignition so the car could not
be started. The third key has now been destroyed and no
further problems are being experienced.
12
EFTA00577672
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
71ST STREET
STATUS ITEM COMMENT
+ Update 1. Safe Room Bolt i) 13/12 - Bolts Arrived & installed — see attached pictures.
> Update 2. Security DSL Line ii) 27/11 - The DSL line to the security cameras in the office
have been hooked up. The receiving end needs to be installed
in Richard's house scheduled for 2 Dec. Marc Lundberg is
able to install a hardware firewall to keep the line more
secure - advised cost will be approx. $1,000.00, a software
firewall has already been installed and will keep the line
secure until we install the hardware.
> JE plse advise 13/12 Both DSL lines have been installed but the software
for the security has not been loaded. JE to approve this prior
to software being loaded.
13/12 — Marc will need to configure the hardware firewall
once the software has been installed.
+ Update 3. Lighting iii) 13/12 — JE met with Rockwell Group week of 4 Dec.
+ Plse advise Plse advise how you would like Nick to pursue this matter.
13
EFTA00577673
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
+ NC 4. Surveillance Cameras 3rd Fir iv) 13/12 - 2 quotes for surveillance of the 3rd fir which will
be based in the safe room previously supplied. This will
+ Would JE like to be an independent surveillance system from the remainder
proceed? of the house. The cameras will only be accessible from the
safe room.
+ NC 5. Hot Water System - Landes v) 27/11 - Richard is obtaining a quotation and proposal to
Siemens have a temperature sensor installed for a domestic hot
water system which links back to the computer system.
This would enable Richard to control and regulate the
domestic hot water — expected 16 Dec.
+ Update 6. Grohe Master Shower vi) 27/11 — Richard disassembled valve & cleaned inlet
Thermostatic Valve screen thermo element cartridge — this has increased the
valve operation & water became hot a lot faster and is
currently running at its optimum level. Parts have been
ordered to see if helps with temperature.
+ JE plse advise 13/12 — Parts have now been installed. From switching on
the tap it takes 2 minutes for the water to heat up to the
correct temperature.
+ Update 7. Flowers viii) 13/12 — There are now three people we can use for the
flowers — Dennis, Flower Shop & Susan Edgar
Productions whom Nick met with.
+ JE plse confirm Please confirm if you would like flowers at 71st if you will
be staying more than 2 days.
14
EFTA00577674
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
+ Lpdate 8. Antennae Company ix) 13/12 — Darren has checked background of antennae
company and everything seems to be in order. Can NS
+ JE plse confirm now arrange a meeting betw. them and Sawyers with
regard to the communication system for 71".
+ Update 9. Panic Buttons x) 13/12 — Panic buttons located in the following areas:
a. Lower entrance handrail on left side
b. Upper entrance handrail right side
c. 1" Floor service corridor right outside staff lift.
d. Master bedroom stairs 2nd floor landing.
e. Old master bedroom now sitting room on wall by the
front door.
f. 1" Floor security desk.
DECORATING
+ NC 8. Coloured Boards for entryway vii) Complete
+ Update 9. Converting part of basement in viii) 13/12 — Quotes received — Charles Miller is looking into
to staff quarters these quotes as the quotes were higher than expected.
Charles spoke to Doug & Brian and advised quotes
received were ballpark estimates for conversion, and once
JE decides which option he would like to pursue, a precise
quotation will be drawn up. The quotes differ because
some items were left out of the one quote.
15
EFTA00577675
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
•; NC 7. Redecoration of living room and ix) 27/11 - Miller says that he is awaiting full electrical plan
MBR from Pinto office so that the can see the scope of work.
13/12 — The redecoration will commence in the new year.
Still waiting for Pinto's office to supply info.
13/12 — Charles advised he is still waiting for Pinto's
office to supply the info. The work cannot commence until
the electrical plan has been received.
+ Update 8. Sarah and Picture of x) 13/12 — Complete.
16
EFTA00577676
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
AEROPLANES
STATUS ITEM COMMENT
> Update I. GIIB Stage III i) 13/12 - Ops 2 inspection completed. Ops.
ii) 13/12 — Loaner APU installed due to high oil consumption
& light cabin smoking on the ground. Our unit is due back
from Dallas Airmotive in January.
iii) 13/12 — Aircraft Lease offer declined.
iv) 13/12 — Quiet Technology Aerospace still awaiting FAA
approval — this is best option for performance, weight &
least modification to the aircraft.
> Update 2. Operational Manual v) 27/11 — Inspector assured Larry M that RVSM / MNPS
Letter of Authorization would be received by the end of the
year.
+ Update 3. 727 Interior vi) 27/11 - Florida Flight viewed 727 to bid on interior removal
and re-installation including modifying aft lavatory for
shower — one quote has arrived minus the shower
component form FLA interiors — The shower section of the
quote should arrive 1st week Dec. The co. Lou Martin was
due to see the plane Dec 2 to be able to quote on the job but
this needs to be rescheduled as the plane will be in NY
17
EFTA00577677
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
vii) 13/12 — Computer & monitor have been removed per JE to
be replaced by CD stereo only. Please advise where
computer & monitor are to be sent.
4 JE plse advise viii) 13/12 — Replacement sink for aft lavatory ready to install —
requires 8 man hours.
ix) 5/12 — Larry is selecting towel racks for fore & aft lays to
be plated & installed, he also has plastic samples for JE to
view for office desk cover. Sample "7" cushions and seat
back wedges being cut and ready for JE to try for office
chair 11 Dec.
JE sampled various cushions — did not like, Larry is
working on obtaining further cushions.
x) 13/12 — January work scope with Jet Aviation to include:
a. Sealing all pocket door voids to quiet during taxi &
flight.
b. Making aft stateroom pocket door more insulated to
noise.
c. Concealing bookshelf speakers in office and forward
salon — Larry M will discuss with JE.
d. Hide the subwoofer in the office.
e. Rework of office chair per test cushions.
18
EFTA00577678
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
xi) 13/12 — Lou Martin to visit aircraft when next in PB for
roman shades & aft lavatory shower modification.
xii) 13/12 — Interior removal & re-installation of the "C" check
is still out for bidding.
xiii) 13/12 — August 2003 work:
a. Pacific Gas Turbines selected to do work on the No. 2
engine high pressure compressor.
b. "C" check will be compiled at Flightstar JAX.
xiv) 13/12 — SFAR 88 (Fuel Tanks) — received relief from
Dugan for the winglets and BFGoodrich for engine mods.
Currently working on all other STC's and modifications in
compliance — no problems foreseen just time consuming. At
FAA mtg in Nov.
+ Update 4. Helicopter xv) 13/12 - Now in Tennessee. Expected completion Jan 15 Inc
a/c floats wire strike kit, High visibility crew doors and
Bose headsets throughout + 2 scoop tail rotor modification.
Training is scheduled Jan 27'h for 5 days.
19
EFTA00577679
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STAFF
STATUS ITEM COMMENT
+ Update 1. Patrick & Evelyn i) 13/12 - Patrick & Evelyn will now be staying in Palm
Beach as the management couple. JE has agreed to pay
Patrick $3,000.00 p/m.
4 NC 2. Rick Harrington ii) Currently earning $125k. How would you like to proceed
+ JE plse advise with Rick?
4 Update 3. South African Candidates iii) 13/12 - Video cassette of three final candidates given to
for JE to view at LSJ. Now that Evelyn & Patrick
> JE plse advise are staying in Palm Beach would JE like to decide about a
couple for ZOITO from the 3 South African candidates: We
would be able to obtain tickets for approximately
$1,000.00 return p/p
a) Andrew & Gidi
b) Fred & Wilma Da Silva
c) Brendan & Nicolene
4 NC 4. Bill Hammond iv) 27/11 — JE said that he would contact directly
+ NC 5. Helicopter Pilot —Nicholas v) 27/11 - He is interested in the position. Nicolas sd that
until the summer he would not be busy with the Navy
contract, and so he could look after the helicopter and fly
it. He has one assignment for the navy in Jan for a week.
4 JE plse advise Nicolas also sd that he had lots of holiday due to him
which he could a I for and use his holida time to work
20
EFTA00577680
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
for JE. Plse advise how you want to proceed.
•> NC 6. Pilot — Peter Rathgeb vi) 13/12 - Larry V still talking to him and he is thinking
about quitting United Airlines.
NC 7. Pilot Search vii) 13/12 - Larry has advised he will wait for a decision on
Bill Hammond and/or Pete before contacting a pilot
headhunter.
•> NC 8. Hugo's Agency in Italy viii) 27/11 — GM obtained the number from Hugo for his staff
agency. GM called the agency the person she spoke with
advised that she needs to look for people who would be
willing to move to the states — GM will follow up lst week
Dec to see if she has any suitable couples.
13/12 - GM still not heard back.
> NC 9. Flavio ix) 13/12 - GM has still not heard back yet from Flavio.
21
EFTA00577681
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
GENERAL
STATUS ITEM COMMENT
Update 1. Palace in Morocco i) 27/11 — GM called Nina Stevens, and Nina said that she
would call back with a number. She has not called back
yet.
13/12 — GM has left a message for Ambassador Jaidi and
has sent a letter with all the info.
+ Update 2. Medical Training for all Houses ii) 13/12 - Tom is happy to provide training for staff in NY
but will need to take a course to qualify him as instructor.
He will be unable to provide training before January.
+ JE plse advise Would JE prefer sourcing someone else?
+ Update 3. Mercedes Guard Car iii) 13/12 — This has been approved for purchase by JE.
Which property should receive the guard car? JE plse
+ JE plse advise advise.
+ Update 4. Medical Equipment iv) 13/12 — Additional purchases:
a. 71s1 Street — burn kit and eye, skin solution
b. 65th Street — complete first aid box
c. Zorro — first aid box for stings, mosquitoes, snakes,
wasps and bees, and a first aid blister box kit.
d. Palm Beach — a cycling road rash kit and a new
medical kit
e. 727 — a suture and syringe medical kit as well as an
emergency dental kit.
22
EFTA00577682
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
KINNERTON STREET
STATUS ITEM COMMENT
Update 1. Range Rover i) 13/12 — Siemens car phone is only available in Europe and
works on GSM network. Range Rover USA is only
installing 12
/ watt regular cellphones in the State side
market.
+ Update 2. Defibrillator ii) 13/12 — This has arrived in London and is being delivered
by FedEx today (13/12) and will be kept with remainder of
first aid kit in the "green" bathroom cabinet.
23
EFTA00577683
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
ZORRO RANCH
STATUS ITEM COMMENT
+ NC 1. Pew i) Arms of the pews have been constructed. Mike will then
stain with color JE picked. Expected completion 18 Dec.
+ Update 2. Water Pump ii) 13/12 — Water pump is in place.
+ Update 3. Security Gate iii) Professional Security (Frank) is working on a price to dig
the trench for the security cameras. Mano could dig the
trench but he is currently working digging the line for the
new water pipe and he would only be able to start digging
the security trench in 3 to 4 weeks. He will have finished
digging around 15th Dec but he has cars to mend etc —
expect the quotation by 8 Dec.
iv) 13/12 - can dig the line once the water line is in,
approx. January 3rd Shannon talked to Automatic Access
and they are sending a sketch of the proposed gate should
have 13 Dec. As at 13h30, Shannon still did not have the
sketch and is still chasing.
v) 13/12 - All the equipment for the security camera system
will be delivered 12/16 Mano will need to dig the trench
then the camera company and come back and install. All
equip. has been delivered. Mano will dig trench once
water line trench is complete.
24
EFTA00577684
FORTNIGHTLY REPORT
FRIDAY 13 DECEMBER
STATUS ITEM COMMENT
•> NC 4. Entry Gate vi) 27/11 - "Z". Should have by 15 Dec. Delayed until 2O
Dec.
t ptiak vii) 13/12 - Lights have been rehung but Shannon's digital
camera is not working. She is purchasing a new camera
and will send the pictures as soon as she can.
+ NC 5. Fountain viii) 13/12 — Additional more complete dimensions sent to
ℹ️ Document Details
SHA-256
1ebeff1b9ecc786408d26454dc296d3ca7551c9d59788738189021a6416dc63b
Bates Number
EFTA00577661
Dataset
DataSet-9
Document Type
document
Pages
41
Comments 0