From: Jeffrey Epstein <[email protected]>
To: Larry Visoski
Subject: Re: G-IV
Date: Mon, 23 Dec 2013 14:03:18 +0000
Inline-Images: IMG_3119.jpg; IMG_2504.jpg; IMG_0815.jpg; IMG_8182.jpg; IMG_5673.jpg;
IMG_5057.jpg; IMG_7443.jpg
lets not rush, .
On Mon, Dec 23, 2013 at 8:18 AM, Larry Visoski c wrote:
Photos of wing painting,
Jeffrey
Update from paint shop this morning,
GIV should be done Dec 24th late afternoon, they had delays.
The earlier messages projected the plane for dec27 th
Sent from my iPhone
Begin forwarded message:
From: Cory Moses <1
Date: December 23, 2013 at 8:21:05 AM AST
To: "
Cc: Tyson Grenzebach Blake Bowen
Subject: G-IV
Good morning Larry,
As of now wings are sanded, NC is being masked and we are preparing to start painting wings. Worse case senario is
we will be pulling trigger at 10AM hopefully sooner. The base takes 2 hours to dry before I can clear, the dry time per
tech data sheet is 16 hours for clear.What time were you wanting to pick up your NC on 24th of December? If you
could work it into your schedule to pick it up later In afternoon that would be great. We are doing everything we can to
try to get you your NC asap. I wanna thank you for your patience and support through this situation.
Please advise with your plans.
Regards,
Cory Moses
Associated Painters Inc
Paint Operations Supervisor
Sent from my iPhone
Begin forwarded message:
EFTA01140278
From: Cory Moses
Date: December 22 2013 at 8:26:55 PM AST
To: "
Cc: T son Grenzebach , Blake Bowen
Subject: G-IV
Good evening Lany ,
We are a little behind schedule, we are taking every precaution possible to ensure there is no more issues
with wings or any further paint failures. Per tech data sheets the high build primer requires at least 12 hour
dry time before sanding. I made the decision to let the primer sit for 24 hours before sanding to ensure it was
dry and guarantee proper adhesion. As you can see from the pies I sent the left wing is completely sanded
and the right wing is about half sanded. To be 100% honest and not beat around the bush with you, with this
week being Christmas I don't see your A/C being complete until Friday. We will finish sanding tomorrow and
take mil readings and average paint thickness to be sure to stay with in our limitations. We will then un mask
A/C entirely and wash re mask and paint wings tomorrow or 1st thing Christmas Eve morning I am
personally going to paint it. I apologize if this puts a damper on your plans more then this entire situation
already has. Possibly could be sooner then Friday. Please advise with your plans
Regards,
Cory Moses
Associated Painters Inc
Paint erations Supervisor
Sent from my iPhone
EFTA01140279
EFTA01140280
•
a
EFTA01140281
EFTA01140282
EFTA01140283
EFTA01140284
EFTA01140285
***********************************************************
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
EFTA01140286
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation®gmail.com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01140287
ℹ️ Document Details
SHA-256
391e50bc93887336086e597091663e47969ab5dc74ec9ca1b30e7293a440d1e4
Bates Number
EFTA01140278
Dataset
DataSet-9
Document Type
document
Pages
10
Comments 0