📄 Extracted Text (1,072 words)
Globaltech
Memorandum
To: Emad Hanna/NYSG
Subject: LSJ Pathway Lighting and Utility Trench
Date: July 15, 2005
Prepared By: Paul Gandy/Globaltech
Introduction
We have prepared a preliminary selection and budgetary estimate for installing
pathway lighting for all outdoor pathways at LSJ. The intent of the lighting project
is to provide illumination of the immediate pathway area to allow visibility of all
pathway segments at night.
The original scope of the preliminary estimate was to provide information for the
pathway lighting project only. However, it was brought to our attention that future
utilities would be extended along the paths for irrigation water, potable water,
power, communication and control, etc. For this reason it might be prudent to
consider constructing the utility duct bank (all utilities in a common trench) at the
same time as the lighting since similar construction equipment (trencher) would
be needed for both projects.
A summary of the two approaches follows:
Description Lighting Only Lightina and Ductbank
Construction Time 4 months 9 months
Budget Estimate $ 430,000 $1,000,000
Each of the above amounts includes 10-20% for engineering, legal, and
permitting fees. A detailed estimate of the above options is included in the
attached spreadsheet. It should be noted that several preliminary assumptions
were made in arriving at the scope of the project. Costs and scope could vary
based on final design and project specifics.
4722 NW Boca Raton Blvd, Suite C103, Boca Raton, FL 33431
Telephone: 561-997-6433 Fax: 561-997-5811
EFTA00586314
Memorandum
Pathway Lighting
June 21, 2005
Lighting description
For the purpose of this estimate we assumed the use of 'bollard' style lighting
fixtures which are between 36" and 48" in height. The primary reason for the
shorter fixtures (as opposed to pole mounted types) is to limit the effects of wind
damage and to control the amount of stray light. From a tour of the site it was
decided that the fixtures would be installed in most every case on the high side of
the path where the additional height of the retaining wall can be used to
advantage. This would also alleviate the need to trench in rock for the individual
light circuits because there is more soil adjacent to the retaining wall on the high
side of the path. Hand digging is possible at this location. Trenching for the main
electrical feeders would still be required in the pathways.
To serve the light fixture power requirements we are assuming the installation of
480 volt main feeders in the pathways with step-down transformers located
approximately at 700 foot intervals. From each transformer the lower voltage
(120 or 208 volts) would be distributed to the individual fixtures. We have also
allowed a budget item for remotely controlling banks of fixtures (by pathway
segment or transformer groups) from a central location so that all fixtures will not
need to be illuminated at once.
Brochures for representative fixtures are attached. We recognize that the actual
selection process is very subjective and could alter the type and spacing of the
fixtures. The following are assumptions used in the layout of the fixtures:
Separation: 50 feet
Quantity: 380
Voltage: 120/208 v
Wattage: 60 (halogen or incandescent)
Material: Aluminum or Stainless Steel
Mounting: Concrete base slab
Total power consumption with all fixtures illuminated is approximately 22.8 kW.
Trenching Description
Due to the nature of the rock on LSJ, trenching is the controlling factor in the
schedule and accounts for 25-35% of the budget. It is assumed that rock will be
encountered for 80% of the trench path. As mentioned above, two approaches
2
EFTA00586315
Memorandum
Pathway Lighting
June 21, 2005
were considered — lighting only and lighting with the installation of a duct bank for
present and future services.
If lighting only is installed, a single narrow cut will be required to install one 4-inch
power conduit and one 2-inch control conduit along the pathways. This accounts
for the reduced schedule and much of the reduced cost. If a utility trench is
installed the following is included:
Trench width: 36"
Trench depth: 18" minimum
Progress per day: 50 feet
Total installation time: 9 months
Conduits:
• 4" 480 volt power (4-wire)
• 2" lighting power (branch only)
• 2" Network-F/O
• 2" Communication
• 2" Irrigation
• 2" Potable Water
• 4" Spare
Pull boxes (concrete) will be installed at 500-700 foot intervals to accommodate
installation of conductors.
It is assumed that the Owner will rent a trencher for the duration of the project
and that the Owner's forces, along with existing equipment on site, will excavate
the trench and install the conduits. As shown in the attached spreadsheet, an
electrical contractor will be employed to do the electrical work. The largest
expense associated with the trenching effort is associated with tooth wear on the
cutting wheel. Rock of the type found on LSJ could use between one and two
sets of teeth per day at approximately $500 per set for the utility trench.
While there are 19,300 feet of pathway we have assumed that the utility trench
would need to extend only along 15,500 feet of that distance in what could be
considered a main loop to service outlying building and "outposts". The smaller
and dead-end pathways would not need a main utility trench.
The budget for the utility trench assumes that only 480 volt power conductors are
installed at this time. Under this option the conductors are larger (to
3
EFTA00586316
Memorandum
Pathway Lighting
June 21, 2005
accommodate future facilities) than the lighting-only option. Network and
communications conduits would be empty until future need.
One note of importance to the above considerations is that it has been assumed
that trenching needs to occur along the pathways for the major utilities. This has
been discussed in the past as an advantage because it allows a 'pathway' and
access road for installing the utilities as opposed to a 'line-of-site' approach
which would involve trenching along the vertical incline of the hill side. We have
assumed using this method to a very minor degree in feeding some of the
lighting circuits. Using this route for the primary utility trench may or may not be a
cost saving factor however it may also prove more difficult to permit as the paths
are already existing.
Once some preliminary decisions are made, a more detailed study could be
employed to determine if a combination of the above methods could be used to
save costs and improve on scheduling.
4
EFTA00586317
ℹ️ Document Details
SHA-256
3fd5d1600b0e4689535b8b6e5f5e8781e2b360e9e58d4797a5d761f60e137f06
Bates Number
EFTA00586314
Dataset
DataSet-9
Document Type
document
Pages
4
Comments 0