Epstein Residence July 29, 2013
9 East 71' Street
New York, N.Y 10021
Attn: Richard Barnett
Re: Cooling Tower & Chiller Replacement, Project Time Line
Project Duration: 17 Working Days, Including Sunday Rig
22nd.
Project Dates: Start — August 1S1 and complete August
Project Time Line
• August I': Prep cooling towers & chiller for removal.
• August 2nd: Remove piping and wiring for towers, demo of old Carrier chiller.
• August 4th: Remove old cooling towers from roof and rig new towers in place,
continue demo of chiller.
• August 5th: Start installing new piping and wiring for new towers.
• August 6'h: Remove old chiller and set new chiller in place, start installing new
piping and wiring for new towers.
• August 7th: Continue new piping and wiring for chillers and towers.
• August 8th: Continue new piping and wiring for chillers and towers.
• August 9th: Continue new piping and wiring for chillers and towers.
• August 12th: Continue new piping and wiring for chillers, break down remote
cooling tower sump.
• August 13th: Start building new remote sump; continue piping and wiring for
chiller.
• August 14th: Continue building new remote sump; continue piping and wiring for
chiller.
• August 15th: Continue building new remote sump; continue piping and wiring for
chiller.
• August 16th: Complete building remote sump, continue piping and wiring for
chiller.
• August 19th: Start and finish piping for remote sump, complete chiller piping and
wiring.
• August 20th: Insulate piping & clean off job site.
• August 21St: Finish insulation of piping, start up and commissioning of new
cooling tower & chiller, water balancing @ chillers.
EFTA01102367
• August 22nd: Completion of project. (Best Scenario)
• August 26'h: Completion of project (Normal schedule)
EFTA01102368
ℹ️ Document Details
SHA-256
47d9121c42e416349851eec7d00ebb30ede74b5bcf1b42fc8ba023ecbd3a690d
Bates Number
EFTA01102367
Dataset
DataSet-9
Type
document
Pages
2
💬 Comments 0