JPK DEVELOPMENT
RESIDENTIAL AND COMMERCIAL CONSTRUCTION
6501 RED HOOK PLAZA SUITE 201, ST THOMAS 00802
TO: LSJ
FOR :2 new bath showers enclosed
SCOPE:
1. Build scaffolding to facilitated new stone walls
2. Remove coral stone on floors
3. Form inside of new exterior walls $3,960
4. JPK to provide forming materials and rebar
5. Walls to be of stone to match existing — stone provided by LSJ $8,970
6. JPK to build two custom shutters and frames painted to match existing $3,800
7. JPK to tile baths floor to ceiling with tile supplied by LSJ -- 589 SF $6,739.20
8. JPK to seal tile with sealer provided by LSJ $589
9. JPK to form and pour two concrete roofs and seal them with Vulkem roof coating - LSJ to
provide concrete $6,280
10. JPK to install effis to match existing materials and labor included $7,780
11. JPK to plumb new fixtures provided by LSJ $1,320
12. JPK to install 2 glass shower doors provided by LSJ $880
13. JPK to construct new interior ceiling with Dura rock and plaster finish 3,640
14. JPK to construct bench and shelf in CBffl with tile finish $880
15. Construct bench and niche in CB#2 with tile finish $880
16. LSJ to provide dumpster for trash
17. Work to be done in a safe and professional manor adhering to all OSHA regulations
18. Daily clean-up will be performed to maintain a clean work site
Sub total $45,718.20
Overhead and profit $6,857.73
GRT 2,628.79
Total cost $55,204.72
40% deposit to start work. Time frame 1.5 months construction time depending on availability of
materials.
EFTA00804924
ℹ️ Document Details
SHA-256
5af1eca79964a2b26b8f0149d70d4a7a0264c8bfbc8b955b9c747f1c0ba2ec38
Bates Number
EFTA00804924
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0