📄 Extracted Text (423 words)
NEPTUNE LLC
358 EL BRILLO WAY
PALM BEACH, FLORIDA
2ND FLOOR STRUCTURAL REPAIRS
Preliminary Construction Budget
9/8/2015
Description Cost
Division One
Project supervision ( $2,000.00 / 6 weeks ) $ 12,000.00
Engineering allowance $ 4,000.00
Floor protection / dust curtains including garage $ 800.00
General Labor (1labor x $600./wk. Final cleaning $600. $ 4,200.00
Dumpster $300. Porta Jon $190. $ 490.00
Blueprint reproduction $ 200.00
Division Two
Demolition & disposal fees $ 4,275.00
Division Four
Bathroom Statuary Marble ( 2 ) shower, main floor and wall Statuary material $ 81,866.70
Bathroom marble installation ( mudset installation ) $ 26,960.00
Division Six
Structural work "ALLOWANCE" est 3 carpenters x $60. / hr. Material TBD $ 28,800.00
Post shore rental ( 8 ) $ 800.00
Baseboard, crown, door and window casings removal and reinstallation $ 2,500.00
Interior doors ( 5 ) remove / reinstall square and plumb $300. / door x 5 $ 1,500.00
Drywall and Duraroc in hall, 2 bathrooms, 2 bedrooms and garage ceiling $ 7,444.15
Bathroom vanity cabinets ( 2 ) remove / reinstall after marble installation $ 1,600.00
Division Seven
Division eight
Replace 2 bathroom mirrors $ 500.00
Division nine
Carpet: remove / reinstall after work is completed $ 1,200.00
Priming and painting walls and trim: 2 bedrooms, hall, stairwell & garage ceiling $ 2,500.00
Division ten
Bath accessories removal and reinstallation $ 180.00
Division fifteen
Plumbing work; remove fixtures, reinstall fixtures, new shower pans $ 8,500.00
Division sixteen
Electrical work : remove / reinstall bathroom light fixtures $ 500.00
Subtotal all costs $ 190,815.85
Permit fees 3% Allowance $ 5,724.47
GC Overhead and profit 18% $ 35,377.26
General Liability ins. @ 1% $ 1,908.16
Total estimated budget cost $ 233,825.74
EFTA01191266
QUALIFICATIONS AND ASSUMPTIONS:
This budget excludes: Weekend and overtime hours, additional Building Dept. plan review comments and revision fees,
Rotted unforseen framing, truss, steel I beams, MEP hidden or unforseen existing conditions ie: Plumb. Elec and HVAC
rough. Any lead or asbestos testing, abatement and remidiation.
Any additional changes in scope from origonal approved plan will be inplimented after Owners approval.
Project Supervision is based on 6 week duration. Any extension of time due to Owner changes, added scope, unforeseen
conditions or Building Deptment delays will be billed at $2,000.00 per week.
City fees are included as allowances and will be billed at actual cost.
Pay schedule:
Deposit of $100,000.00 due at contract signing for engineering, permitting, demo and MEP sub deposits.
$100,000.00 progress payment due at mobilization.
$33,825.74 payment due at completion.
Owner's acceptance and approval Date
EFTA01191267
ℹ️ Document Details
SHA-256
6218e7ef77d16fa1c9a8d455960d68026c4bd9cdd9ffa93a6c629fd3ce72570b
Bates Number
EFTA01191266
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0