MINOR COASTAL ZONE MANAGEMENT PERMIT NO. CZT-25-10L
1. AUTHORITY. This permit is issued by the Commissioner of the Department of Planning
and Natural Resources and is administered and monitored by the Department pursuant to
Title 12, Chapter 21 of the Virgin Islands Code. As herein, "Permittor" is the Government
of the Virgin Islands and "Permittee" LSJ, LLC.
2. SCOPE. This permit allows the site preparation and construction of a 27' x 70' swimming
pool with a 2,000 &cabana, coral stone deck, living space, rest room, pool equipment room
and a 1,800 ft2 music room. This project is located at parcel A Little St. James, St. Thomas,
Virgin Islands.
3. TERM. This permit is effective upon its signing by the Commissioner of the Department of
Planning and Natural Resources, pursuant to VI Code, Title 12, Chapter 21. Authorization
for construction under this permit will expire if he Permittee fails to commence work within
twelve (12) months from the date this permit becomes effective.
4. DOCUMENTS INCORPORATED BY REFERENCE.
EXHIBIT A - CZM Permit Application dated April 8, 2010
EXHIBIT 8 - Required document submittal (deed, tax letter and maps)
EXHIBIT C - Site plan and Drawings dated July 7, 2010.
5. GENERAL CONDITIONS.
(a) Liability. The Permittee agrees to assume full and complete responsibility for all
liability to any person or persons, including employees, as a result of its control ofthe
area described in Paragraph 2 of this permit, and all improvements thereon (which
area and improvements are herein after referred to as" the premises") and to hold the
Permittor free and harmless from civil or other liability of any kind during the time
the permittee is in control of the premises pursuant to this permit.
(b) Personal Property and Damage. All personal property of any kind or description
whatsoever, located on the premises will be there at the Permittee's sole risk.
(c) Assignments or Transfer, This permit may not be transferred or assigned except as
provided in Section 910-15 of the Regulations of the Coastal Zone Management Act
(d) Permit to be displayed. A placard evidencing the permit shall be posted in a
conspicuous place at the project site during the entire period of work.
(e) Reliance on Information and Data. The permittee affirms that the information, and
EFTA01091521
CZT-25-10L
data which he/she provided in connection with his/her permit application is true and
accurate, and acknowledges that if subsequent to the effective date of this permit
such information and data proves to be false or inaccurate, the permit may be
modified, suspended or revoked in whole or in part, and that the Commissioner may,
in addition, institute appropriate legal action.
(0 Pevelonment to be Commenced. Any and all development approved by this Coastal
Zone Management Permit shall be commenced within twelve (12) months from the
date this permit becomes effective. Failure to perform substantial work within such
period and thereafter until completion of construction will cause the permit to lapse
and render it null and void unless an extension is granted by the Commissioner.
(g) Notification of Completion. Upon completion of any activity authorized or required
by this Coastal Zone Management Permit, the permittee shall promptly so notify the
Director of the Division of CZM ("The Director") and where the service of a
professional engineer were required in undertaking the activity, a certification of
compliance provided by the project engineer that the plans and specifications of the
project and all applicable Virgin Islands Code requirements have been met, shall be
filed with the Director.
(h) Inspection. The Commissioner or his authorized agents or representatives shall have
the power to enter at reasonable time during projects working hours upon any lands
or waters for which a Coastal Zone Permit has been issued. The Permittee shall
permit such entry for the purpose of inspection and ascertaining compliance with the
terms and conditions of said Coastal Zone Management Permit. The Permittee shall
provide access to such records as the Commissioner in the performance of his duties
under the Act may require the Permittee to maintain. Such records may be examined
and copies shall be submitted to the Commissioner upon request
(i) Conditions of premises. The development authorized by this permit shall be
maintained in a safe, attractive and satisfactory condition and in accordance with the
description, plans or drawings approved by the Commissioner.
(j) Restoration of Area. The pennittee, upon revocation or expiration of the permit,
shall upon order of the Commissioner, and his sole discretion, remove all structures
authorized by the permit and restore the area to its original condition, and/or modify
such structures, and/or comply with any directive of the Commissioner in satisfying
the original permit condition in such time and manner as the Commissioner may
direct.
(k) Notices. All notices sent or required to be sent hereunder must be certified mail,
return receipt requested. If addressed to the permittor, same shall be sent to the
Commissioner of the Department of Planning and Natural Resources, 8100 Lindberg
EFTA01091522
CZT-25.101.
Bay Suite 61, St. Thomas, VI 00802 or to such place as the Pennittor may herein
after designate by certified mail. If addressed to the Permittee, same shall be sent to
LSJ, LLC, 6100 Red Hook Quarter, Suite B, St. Thomas, VI 00802 or to such place
as the Permittee may hereinafter designate by certified mail, return receipt requested.
(1) Nonwaiver, One or more waivers by the Pennittor of any covenant or condition of
this permit shall not be construed as a waiver or breach of the covenant or condition,
and the consent or approval of the Pennittor to or of any acts by the Pennittee
requiring the Permittor's consent or approval shall not be construed as approval of
any subsequent similar act by the Permittee.
(m) Revocation. It is specifically understood that all foregoing covenants and
agreements, as well as other terms and special conditions hereby agreed to by
Permittee, are to be well and faithfully kept by Permittee and that any failure by
Permittee to keep same will result in revocation of this permit.
(n) Other Approval. lithe development covered under this permit requires separate and
distinct approval from the United States Government or any agency, department,
commission or bureau thereof, then no development or occupancy is allowed under
this permit until such permits or approvals have been obtained.
(o) Abandonment. If the Permittee abandons, deserts or vacates the premises or
discontinues its operations at the premises for a period totaling six (6) consecutive
months, then the permit will terminate automatically and be rendered null and void.
(p) Damage and Repair of Premises Described in Paragraph 2. In the event of damage to
or destruction of the premises described in Paragraph 2 hereof, repair work may be
done only after a request to do so has been submitted in writing to the Department
and permission in writing has been granted. Repair must duplicate the original work,
and must be in accordance with applicable law, rules and regulations.
(q) Signatures on the Permit Document. The applicant shall sign and return the permit
document to the Department within sixty (60) days of receipt thereof. Failure to
return the signed permit within the time period specified herein will be considered a
rejection of the terms and conditions of the permit and will render the offer of the
permit null and void, unless a written extension is requested and granted.
6. SPECIAL CONDITIONS,
A. The Division of Coastal Zone Management shall be notified in
writing at least forty-eight (48) hours before work commences.
B. This permit is valid only for work as stated in Paragraph 2 "Scope;"
EFTA01091523
C21'45-10L
Work must adhere to the details per the stamped, approved drawings.
C. A permit placard displaying the Coastal Zone Management (CZM)
permit no. CZT-25-10L shall be displayed in a conspicuous location
on site prior the commencement of work.
D. All other necessary permits, including construction permits from the Division of
Building Permits, shall be obtained prior to the commencement of work.
E. Site disturbance shall be limited to areas designated on the approved drawings; no
development activities may occur outside the footprint of the approved permit.
F. Erosion/Sediment control measures shall be installed and maintained until all
development activities are completed. All excavated areas shall be protectively
bermed to prevent runoff.
G. Silt fencing must be installed with steel posts and wire fence support as described in
the 2002 Environmental Protection Handbook.
H. The Pemilttee will develop a plan to address concerns regarding habitat rehabilitation
and restoration with Department staff.
L Upon discovery of any archaeological or historical site, or human burial site or
remains upon private lands, the owner or his representative shall immediately notify
the State Historic Preservation Office verbally and in writing.
EFTA01091524
CZT-25-10L
On tic Day ° 010 the Department of Planning and Natural Resources
h issues Minor Pennit No. CZT-25-10L.
thes
oner
I, the undersigned, have read and understood all terms and conditions established in Permit No.
CZT-25-10L and hereby agree to be bound by the terms and conditions contained therein.
Date
cc: File
EFTA01091525
ℹ️ Document Details
SHA-256
6292f0afef3571a60befc06268ecff3dcc32c8a68799b9ee62e1c06828342325
Bates Number
EFTA01091521
Dataset
DataSet-9
Document Type
document
Pages
5
Comments 0