MINOR COASTAL ZONE MANAGEMENT PERMIT NO. CLI-02-15L
I. AUTHORITY. This permit is issued by the Commissioner of the Department of
Planning and Natural Resources and is administered and monitored by the Department
pursuant to Title 12, Chapter 21, Virgin Islands Code. As herein, "Permittor" is the
Government of the Virgin Islands and "Permittee" is Nautilus, Inc.
2. SCOPE. This permit allows the paving of existing recreational vehicle and pedestrian
pathways. This project is located at parcels A, B & C Little St. James Cay, St. Thomas,
Virgin Islands.
3. TERM. This permit is effective upon its signing by the Commissioner of the
Department of Planning and Natural Resources, pursuant to VI Code, Title 12, Chapter
21. Authorization for construction under this permit will expire if the Permittee fails to
commence work within twelve (12) months from the date this permit becomes effective.
4. DOCUMENTS INCORPORATED BY REFERENCE.
EXHIBIT A - CZM Permit Application signed October 2, 2014
EXHIBIT B - Required document submittal (deed, tax letter and maps).
EXHIBIT C - Site plan and Drawings dated September 18, 2014
5. GENERAL CONDITIONS.
(a) liability. The Permittee agrees to assume full and complete responsibility for all
liability to any person or persons, including employees, as a result of its control of
the area described in Paragraph 2 of this permit, and all improvements thereon
(which area and improvements are herein after referred to as" the premises") and to
hold the Permittor free and harmless from civil or other liability of any kind during
the time the permittee is in control of the premises pursuant to this permit.
(b) Personal Property and Damage. All personal property of any kind or description
whatsoever, located on the premises will be there at the Permittee's sole risk.
(c) Assignments or Transfer. This permit may not be transferred or assigned except as
provided in Section 910-15 of the Regulations of the Coastal Zone Management
Act.
(d) Permit to be displayed. A placard evidencing the permit shall be posted in a
conspicuous place at the project site during the entire period of work.
EFTA01091526
CZJ-02-15L
Nautilus, Inc.
(e) Reliance on Information and Data. The permittee affirms that the information, and
data which he/she provided in connection with his/her permit application is true and
accurate, and acknowledges that if subsequent to the effective date of this permit
such information and data proves to be false or inaccurate, the permit may be
modified, suspended or revoked in whole or in part, and that the Commissioner
may, in addition, institute appropriate legal action.
(f) Development to be Commenced. Any and all development approved by this
Coastal Zone Management Permit shall be commenced within twelve (12) months
from the date this permit becomes effective. Failure to perform substantial work
within such period and thereafter until completion of construction will cause the
permit to lapse and render it null and void unless an extension is granted by the
Commissioner.
(g) Notification of Completion. Upon completion of any activity authorized or
required by this Coastal Zone Management Permit, the permittee shall promptly so
notify the Director of the Division of CZM ("The Director") and where the services
of a professional engineer were required in undertaking the activity, a certification
of compliance provided by the project engineer that the plans and specifications of
the project and all applicable Virgin Islands Code requirements have been met, shall
be filed with the Director.
(h) Inspection. The Commissioner or his authorized agents or representatives shall
have the power to enter at reasonable time during projects working hours upon any
lands or waters for which a Coastal Zone Permit has been issued. The Permittee
shall permit such entry for the purpose of inspection and ascertaining compliance
with the terms and conditions of said Coastal Zone Management Permit. The
Permittee shall provide access to such records as the Commissioner in the
performance of his duties under the Act may require the Permittee to maintain.
Such records may be examined and copies shall be submitted to the Commissioner
upon request.
Conditions of premises. The development authorized by this permit shall be
maintained in a safe, attractive and satisfactory condition and in accordance with
the description, plans or drawings approved by the Commissioner.
Restoration of Area. The permittee, upon revocation or expiration of the permit,
shall upon order of the Commissioner, and his sole discretion, remove all structures
authorized by the permit and restore the area to its original condition, and/or modify
such structures, and/or comply with any directive of the Commissioner in satisfying
the original permit condition in such time and manner as the Commissioner may
direct.
2
EFTA01091527
CZJ-02-15L
Nautilus, Inc.
(k) Notices. All notices sent or required to be sent hereunder must be certified mail,
return receipt requested. If addressed to the pennittor, same shall be sent to the
Commissioner of the Department of Planning and Natural Resources, Cyril E. King
Airport, Second Floor, St. Thomas, VI 00802 or to such place as the Permittor may
herein after designate by certified mail. If addressed to the Permittee, same shall be
sent to Nautiluc, Inc., 6100 Red Hook, Suite B3, St. Thomas, Virgin Islands 00802,
or to such place as the Permittee may hereinafter designate by certified mail, return
receipt requested.
(I) Nonwaiver. One or more waivers by the Permittor of any covenant or condition of
this permit shall not be construed as a waiver or breach of the covenant or
condition, and the consent or approval of the Permittor to or of any acts by the
Permittee requiring the Permittor's consent or approval shall not be construed as
approval of any subsequent similar act by the Permittee.
(m) Revocation. It is specifically understood that all foregoing covenants and
agreements, as well as other terms and special conditions hereby agreed to by
Permittee, are to be well and faithfully kept by Permittee and that any failure by
Permittee to keep same will result in revocation of this permit.
(n) Other Approval. If the development covered under this permit requires separate
and distinct approval from the United States Government or any agency,
department, commission or bureau thereof, then no development or occupancy is
allowed under this permit until such permits or approvals have been obtained.
(o) Abandonment. If the Permittee abandons, deserts or vacates the premises or
discontinues its operations at the premises for a period totaling six (6) consecutive
months, then the permit will terminate automatically and be rendered null and void.
(p) Damage and Repair of Premises Described in Paragraph 2. In the event of damage
to or destruction of the premises described in Paragraph 2 hereof, repair work may
be done only after a request to do so has been submitted in writing to the
Department and permission in writing has been granted. Repair must duplicate the
original work, and must be in accordance with applicable law, rules and regulations.
(q) Signatures on the Permit Document. The applicant shall sign and return the permit
document to the Department within sixty (60) days of receipt thereof. Failure to
return the signed permit within the time period specified herein will be considered a
rejection of the terms and conditions of the permit and will render the offer of the
permit null and void, unless a written extension is requested and granted.
3
EFTA01091528
CZJ-02- I 5I,
Nautilus, Inc.
6. SPECIAL CONDITIONS.
A. The Division of Coastal Zone Management shall be notified in writing
at least forty-eight (48) hours before work commences.
B. The Coastal Zone Management permit placard shall be placed in a
conspicuous location on site as soon as work commences.
C. This permit is valid only for work as stated in Paragraph 2 "Scope"
D. All excavated areas shall employ sediment and erosion control
measures to prevent silt runoff.
E. Site disturbance shall be limited to areas designated on the approved
drawings.
F. All other necessary permits shall be obtained prior to commencement of work.
G. Upon discovery of any archaeological or historical site, or human burial site or
remains upon private lands, the owner or his representative shall immediately notify
the State Historic Preservation Office verbally and in writing.
H. Silt fencing must be installed with steel posts and wire fence support as described in
the 2002 Environmental Protection Handbook.
I. Storm water drainage features installed as part of this permit shall have regular
maintenance to ensure proper operation.
4
EFTA01091529
C2J-02-15L
Nautilus, Inc.
On this '' Day of ,1 u•wtw, 2014 the Department of Planning and Natural Resources
hereby issues Minor CZM Permit No. CZJ-02-15L.
Pierre Oriol
A ti g Commissioner
I, the undersigned, have read and understood all terms and conditions established in Permit No.
CZJ-02-15L and hereby agree to be bound by the terms and conditions contained herein.
Signature Date
cc: File
5
EFTA01091530
ℹ️ Document Details