ESTATE PROGRESS REPORT — September 26, 2003
LSJ
NEXT DATE REVISED
LOCATION COMMENT
ACTION BY BY DATE
JE / MILES
BEACH OFFICE
Entry Road & Circle Entry road & circle being reworked. Miles
In progress
DOCK
Floating Platform and Sand wood and apply wood sealer. Completion by Oct 15. Miles 10/15
Dock
GYM
Gym Main Room External wall to be built on patio, encased with dark wood. JE Miles
wants sample — no work done — no sample ordered. Not started
Flower Pots To be rearranged. Matt/Miles
MAIN CURRENT HOUSE
Lanterns Lanterns in France for LSJ have been damaged in shipment -
some broken glass. Sent to be restored. No completion date
yet.
Lights Lights that shine up & down to be sourced to replace glass Daniel R
hurricane lamps located outside of the house. Daniel found a
line of outdoor lights that he thinks is perfect but slightly
smaller than JE wanted — he is looking to see if he can find the
same but larger.
Courtyard Four lights to be installed in large trees (5 trees total). Bruce White
Christmas lights Christmas lights to be installed in large trees for the season. Bruce White
I
EFTA00577538
ESTATE PROGRESS REPORT — September 26, 2003
LSJ
NEXT DATE REVISED
LOCATION COMMENT
ACTION BY BY DATE
MASTER BEDROOM
MBR Stairs Down to Top half of stairs to be completed by Sept 30. Miles / Stone 8/29 9/30
Beach Masons
Shoe Rack GM to purchase tall shoe rack for MBR. GM
LANDSCAPING / IRRIGATION
MBR / Terrace Area 1. Stone wall to be built as wind break b/w MBR & sea cliff Miles
(above curved steps). The wall to be as high as salt bush. Not started
2. Provisions to be made for planters.
Terrace Area 1. Screens to be built on both sides to enhance the windbreak. Miles 10/10
Platform - MBR Expected completion by Oct 10.
2. Planting to occur in front of platform. Miles
Not started
Wall — Old Heli Pad Construction of the wall to hide old helicopter pad is in Miles
progress. In progress
Miscellaneous Build planter on east facing gym wall. Miles
Not started
New Owner's Road Focus points to be created at road corners. Not started
and Other Areas
Big Trees Approved - 100 trees. Trees are tagged and ready to be pulled We Be Trees, 10/10
for delivery by Oct 10. Inc.
Fruit Trees Mahaffey provided list of suitable fruit trees - approved by Mahaffey /
Madison. Mahaffey to price chosen trees. Madison to select Madison
suitable site for trees on next visit to LSJ.
2
EFTA00577539
ESTATE PROGRESS REPORT — September 26, 2003
LSJ
NEXT DATE REVISED
LOCATION COMMENT
ACTION BY BY DATE
Mulch / Seedlings Approved - container of mulch & seedlings ordered. Delivery Matt 10/10
by Oct 10.
POOL
Rock at Swimming Rock top lowered. Complete
Pool JE to view
KAWASAKI ATV
4x4 Kawasaki ATV 4x4 Kawasaki delivered to LSJ. Complete
JE to view
NANNA
4 Stroke Engine Larry's info on 2 & 4-stroke engines: On hold
1. The 300 hp Yamaha HPDI engine is not avail until mid-Dec.
The noise level will be comparable to the 250 hp Yamaha &
may not be worth the increased weight for the boat only to gain
5 mph in speed. It is certainly worth waiting for the big 4-
stroke engine due out next year — with noticeable vibration &
noise reduction.
2. 225 hp is the largest Yamaha 4 stroke at this time.
3. Mercury Outboards — they are scheduled to announce In Line
6 cylinder 250 hp 4 stroke engine at the Feb 2004 boat show.
This engine will be supercharged & have a growth potential up
to 350-400 hp after reliability has been proven.
JE advised to wait until Jan.
3
EFTA00577540
ESTATE PROGRESS REPORT — September 26, 2003
LSJ
NEXT DATE REVISED
LOCATION COMMENT
ACTION BY BY DATE
Replacement Project in progress. Glue on LSJ. Project to recommence on
Tubes/Fitting Kit + September 26. Completion +/- 10 working days.
teak and fiberglass
FAT CAT
Fat Cat To be renamed Lady G. Documentation sent to USCG for JE
name change. Please advise decision on font & language per
samples sent.
SEAMORE
Re-powering Installation of engine & necessary modifications are ongoing, Boscoe 9/19 1013
Sea trials went well. Expected delivery by Oct 3.
LADY G
Name To be named Lady G II. JE to approve font so that name can be JE
put on console.
CART PATHS
Slip Road to Gym 1. New road to the gym has been cut, stone work around Complete
triangle completed & cactus garden planted. JE to view
2. Stone walls in that area are currently being reworked to make Miles
them similar to the new walls. Ongoing. Ongoing
Approach Road to Width of road near the gym entrance to be reduced. Combined Ongoing
Gym with slip road to gym helipad. Ongoing, currently rebuilding
road to helipad.
4
EFTA00577541
ESTATE PROGRESS REPORT — September 26, 2003
LSJ
NEXT DATE REVISED
LOCATION COMMENT
ACTION BY BY DATE
NEW BUILDING SITES
Grounds 4 areas terraced at new building site. Complete
Cleared Area Seeding Seed has been ordered. Larry has purchased small hand seeder. 9/27
Expected in LSJ Sept 27.
Slatted House Daniel R plans sent to Cimmaron Builders and Steve Roberts JE
for pricing. Cimmaron Builders estimate of $45,500 submitted.
JE to advise. Steve Roberts (SR Builders) waiting for structural
engineer report before submitting quote.
Deer Miles to dart deer & build pen to place them in (cleared area). JE / Miles
JE requested top of hill or preferably, by the beach office where
the picnic tables were. Miles is concerned with how deer will
be fed / supplied water if placed by beach office. Miles to
discuss with JE. Permit requirements to be determined.
TECHNOLOGY/
MISC
Networking Room 2 cable pulled through. Final network drops & wireless Complete
access points installed.
Curtains — Beach New white gauze curtains to be purchased. has arranged
Office purchase of material.
Chaise Lounge / Chaise Lounge - Pinto to decide on furniture.
Furniture - MH
5
EFTA00577542
ESTATE PROGRESS REPORT — September 26, 2003
LSJ
NEXT DATE REVISED
LOCATION COMMENT
ACTION BY BY DATE
Plastic Pots JE wanted plastic pots from the Conran Shop. Can be ordered JE
& can arrive in 2 months. Cost is $625 ea. JE to advise.
Redecoration 1. Wicker furniture options — Pinto / Daniel R to handle.
2. Chosen towel rack forwarded to Daniel R with instructions to
order 5.
FYI: followed up to get delivery dates on items sent to DR to
purchase Sept 15. DR office said that the items would be
ordered week of Sept 22.
Radio on LSJ for St. As per P Hoffman, JE approved St. John Rescue's request of P Hoffinan
John Rescue permission to install a radio inside a building on LSJ. This
approval is subject to a liability review by P Hoffman.
Island Grill Miles to figure out if Viking outdoor grill is feasible for Tiki Miles
houses.
6
EFTA00577543
ESTATE PROGRESS REPORT — September 26, 2003
LSJ
FOR GM EYES ONLY
LSJ
MISCELLANEOUS
Lookout House Approved. Replace bedspread.
Tiki House Two arm chairs and foot stools - awaiting quotes to recover. GM /
Fabric? JEE attached quote. Cathy
Two extra sets of chair cushions. Quote: $40.00 per set. GM
to approve.
Yellow House 1. Make a headboard. Woodshop Complete
2. Cover with same fabric as bedspread. Headboard to go to St. Cathy 10/15
John for covering.
7
EFTA00577544
ℹ️ Document Details
SHA-256
821b6a310d525528a01ed9af23049af9205866b6dc9cc1f2d1bbe5dbcb354a98
Bates Number
EFTA00577538
Dataset
DataSet-9
Document Type
document
Pages
7
Comments 0