JPK DEVELOPMENT
RESIDENTIAL AND COMMERCIAL CONSTRUCTION
ST THOMAS 00802
EMAIL
TO: LSJ
FOR: CONSTRUCTION COSTS TO EXPAND COTTAGE ON GSJ
SCOPE:
1. Demo remaining flooring, windows, and kitchen
2. Site cistern and supervise excavation
3. Excavation to be performed by LSJ
4. Form and pour cistern 16' x 20' x8' deep with footings, 6"slab, 8" walls, 6" slab on top of
cistern with I: rebar 8" oc each way.
5. Concrete to be provided by JPK apx 35 yards
6. JPK to provide forming materials and rebar
7. JPK to provide labor to construct and pour, seal and clean up site
8. LSJ to provide dumpster for trash
9. Waterproofing with hydrolic cement over snap-tie holes, coving at base of wall where cold
joint exists and 2 coats of Throseal cementitious sealer
10. Install /2 " layer of cement board to existing sub floor
11. Install new tile purchased by JPK $3.00 allowance ----625 SF
12. Install new windows and sliders non impact rated
13. Dig and pour 11 footings for new expanded construction
14. Construct new open porch with flat roof between living and bedroom pod
15. Construct new bed room pod out of pressure treated framing 16' x 20' with porch 7' x16'
with shed roof
16. Construct new hip roof on bedroom pod with 3x8 rafters, 1x6 T+G decking, ice and water
shield, 2x4 purlins and galvanized roof to match
17. Finish interior of bedroom cottage with 5/8 green board
18. Create out door shower
19. Kitchen 12 LF with solid surface counter top
20. Create new bath and closet at rear of new pod
21. All materials to be sourced by JPK and purchased by JPK
EFTA00804248
22. Painting by JPK painters
23. Electrical and plumbing by JPK
24. LSJ to provide dumpster and disposal
25. Maintain a clean work site
26. Adhere to all OSHA safety regulations and local building codes
Total cost $170,004.77
EFTA00804249
ℹ️ Document Details
SHA-256
8b03efb5e9a1a0d40188421d22650271b3cd7b399a9e5bc93308061c5938f272
Bates Number
EFTA00804248
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0