Construction Proposal
January 9, 2016
The Owner: LSJ
Little St. James Island
St. Thomas, VI
The Contractor: Betteroads Asphalt LLC
PO Box 301946
St. Thomas, VI 00803
1-8593-IL
The Project: LSJ Crusher Run Test Strip
Little St. James Island
USVI
SCOPE OF WORK:
Provide labor and equipment to place and compact crusher run test strip for owner's observation.
Crusher run material to be provided by owner;
• Test strip area measuring 12ft. (W) x 800ft. (L) x 5in. (D)
TOTAL BASE PRICE: $6,842.40
LSJ Crusher Run Test Strip January 9. 2016 1 of 2
EFTA01087968
Project Totals:
Name Quantity Unit Cost Unit Total Cost
Crusher Run Rest Strip
Materials Placement 250 $7.50 Ton 31,875.00
Compaction 250 $12.50 Ton $3,125.00
Equipment Mobilization 1 $950.00 LS $950.00
Subtotal $5,950.00
Company Overhead & Margin
Company Overhead Percentage 15.00% N/A Percent of Costs $892.50
Grand Total $6,842.40
LSJ Crusher Run Test Ship January 9. 2016 2 of 2
EFTA01087969
ℹ️ Document Details
SHA-256
9a97cbadc53f49454abdb764768cc36c47304fcf58f6233c1dc7bebf98ea75c8
Bates Number
EFTA01087968
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0