Dear Miss Maxwell,Hope you had a good weekend.Site meeting number 14 is what i believe you
want to know each week.Attached also is a progress claim report.Also i would let you know
percentage wise how the construction is progressing,for example, excavation 90%
complete,demolition 20%,bricklaying,concrete,carpentry,roof,doors,
windows,ceilings,floorings.electrical,plumbing,tiling,built-ins,joinery,vanities,painting
etc.Could you please send my last email back as i didnt get to save the weekly house
report.I have been on a lot of building sites and understand construction very well.My last
feelance job was the end construction of a 26000sq house on Long Island.Please let me know
if you require any more information.All the best.Brett.
>From: "G. Max"
>To:
>Date: Sat, 14 Jun 2003 21:19:49 -0400
>Thank you for replying to me so promptly - you may be aware at this point
>that Stefan no longer is working for us
>What I am looking for is an example of a report that you provided to whom
>ever you work for detailing how the construction is progressing on any
>project that you are responsible for. Of course I am not looking for any
>sensitive information so you can delete any area that it would not be
>appropriate for me to have, and send me what I can see.
>Thank you
>Miss Maxwell
Add photos to your e-mail with MSN 8. Get 2 months FREE*.
</x-flowed>
[-- Detached Attachment: "MeetingNo[2].14.doc" --]
[-- Detached Attachment: "ProgressClaimNo[1].11.xls" --]
EFTA00578913
ℹ️ Document Details
SHA-256
d15c4e5353b4d52ce5a7ebe6880db6be63f0fd110224f6447a07b625a9731474
Bates Number
EFTA00578913
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0