72- WATER START END NOTES PHOTO STATUS
DEVELOPMENT
5/6/2014 3/4/19 - Pumping Water into Pond 24/7. Updated Readings will be
forwarded to Casey Cook to confirm progress 3/8/19
966 - PAVING OF START END NOTES PHOTO STATUS
ROADWAY
6/29/2017 2/12/19 - Gilbert Luna (Universal Paving) & his Forman On Site to
Review Final Section of Work. He Proposed Only to "Fix" 2000' -
MH Z to Bull Head. He indicated Fix for Office to Main Gates.
Proposed Work to begin March.
BG has concerns regarding "Fix" & Proposed Start Date, due to
Temps. Recommend late April/May. BG explained Owner would
want New Surface to Run from MH Z to Cattle Guard RC, Office to
Main Gates
BG indicated a payment of 100k, Gilbert Luna would need to sign
Legal Binder. He expressed concerns as requested work would
cost him approx. 100k. He was to review numbers & get back with
BG. As of date & time no contact has been made.
Should we contact Mountain States or another Company to see if Awaiting
they are interested in providing a Proposal for a "Fix"? Response
102 - LUTRON START END NOTES PHOTO STATUS
SYSTEM - MH
2/22/2019 2/22/19 - Forwarded E Mail with Photos to RMC Electric showing
the existing system
Due to weather issues Lutron Rep has cancelled Site Visit to
review existing system 3 times
3/8/19 - Lutron Rep Due On Site 3/8119 - Lutron
Rep Due On
Site
118B PURCHASE START END NOTES PHOTO STATUS
WATER TRUCK
Will review with JE when On Site
118C - PURCHASE START END NOTES PHOTO STATUS
GRADER
Will review with JE when On Site
Pagel
EFTA00811070
134 - POOL PAC START END NOTES PHOTO STATUS
COMPRESSOR - MH
2/2/2019 2/27/2019 2/2/19 - Received Quote to Purchase/Install Pool Pac Compressor
from Honeywell
2/26/19 - Honeywell on Site to Install Compressor
2/27/19 - Compressor Install Running 100%
Complete
136 START END NOTES I S
PI STATUS
REFURBISHMENT
RED HOUSE
1/21/2019 2/1/19 - 1/3 Down - House Incorporated - Demo/Remo Upper &
Lower Levels
2/27/19 - 1st Coat Painting on Wall & Ceiling Complete
2/27/19 - Airpro Installed New Furnace, Condenser/AC Split Unit
will be Installed when Weather Permits
2/28/19 - Installation of Tile Floor Started. Due to very uneven
floors, taking longer that expected
3/1/19 - Installation of Shower Tile in Sm Bathroom Started
3/1/19 - Purchase Shower Tub - Master Bathroom
Granite Ordered
Carpet Ordered
3/5/19 - Fireplace Insert Due On Site
Cabinets On Site - Installed week of 3/11/19
Appliances Due On Site 3/7/19
- WAR. fjj, START END NOTES PHOTO STATUS
2/7/2019 3/8/19 - Repairs Due to be completed Awaiting Repair
Page 2
EFTA00811071
137 - START END NOTES PHOTO STATUS
PURCHASE/INSTALL
FURNACE -STABLES
2/19/2019 2/28/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing Furnace. Furnish/Install 1 Carrier 110,000 BT Furnace in Response
Stables. (2/16/191
2/16/19 - RK requested 10% Discount
2/19/19 - Airpro Discounted 10%
2/21/19 - 50% Deposit Paid to Airpro
12/27/19 - Airpro Installed New Furnace
2/28/19 - Furnace Installed. Running 100%
3/4/19 - Paid Balance to Airpro
Project Total Comic'
138 - START E NOTES PHOTO STATUS
PURCHASE/INSTALL I
AC SPLIT UNIT &
FURNACE - LV'S
HOUSE
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of Awaftlna
Existing Swamp Cooler. Fumish/Install 1 Carrier 4 ton AC Split Unit Response
.and Furnace to LVs House 12/16/19)
2/16/19 - RK requested 10% Discount
2/19/19 - Airpro Discounted 10%
2/21/19 - 50% Deposit Paid to Airpro
2/25/19 - Matenal/Parts Ordered
139 - START END NOTES PHOTO STATUS
PURCHASEJINSTALL
AC SPLIT UNIT &
FURNACE - YELLOW
HOUSE
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing Swamp Cooler. Fumish/Install 1 Carrier 3 ton Furnace to Response
Yellow House (2/16/19)
2/16/19 - RK requested 10% Discount
2/19/19 - Airpro Discounted 10%
2/21/19 - 50% Deposit Paid to Airpro
2/25/19 - Material/Parts Ordered
Page 3
EFTA00811072
140 START END NOTES PHOTO STATUS
PURCHASE/INSTALL
X 6 UNIT HEATERS -
GARAGES RC
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing 6 Heaters. Fumish/Install 6 Sterling Unit Heaters - Response
Garages RC (2/16119)
2/16/19 - RK requested 10% Discount
2/19/19 - Airpro Discounted 10%
.2/21/19 - 50% Deposit Paid to Airpro
2/25/19 - Material/Parts Ordered. Installation expected 3/14/19 Awaiting
Installation
141 - CARPET LODGE START END NOTES PHOTO STATUS
2/11/2019 2/11/19 - JE Approved New Carpet, Blinds/Curtains, Tile in x
Bathrooms & Laundry. New Light Colored Carpet
Have Swatches & Samples to Show when On Site
142 - PHONE SYSTEM • START NOTES PHOTO STATUS
LODGE & LOG
Project Placed On Hold 1/10/18
Are we still to proceed with Verizon Cellular Phone Line for Lodge? Awaiting
Response
Are we still to proceed with Verizon Cellular Phone Line & Solar Awaiting
Generator for Log Cabin? Response
143 - SECURITY START END NOTES PHOTO STATUS
CAMERAS -FRONT
GATES
Existing Security Camera System has Failed. Gates Operational
Reviewing Options - Option 1 Did Not Work as Cellular Provider
was AT&T. Reviewing other Options
Page 4
EFTA00811073
i4 - SEPTIC START I END NOTES PHOTO STATUS
SYSTEMS -RC
12/28/2019 Septic Line to the Tank & the Leaching Field for the BH need
replacing. Roots from Trees have Compromised the Line. The
Adobe is in the same situation
2/28/19 - All RC Septic Tanks, Pumped Out
Gene Basset will forward a Proposal for Removal/Installation New Awaiting
Septic Tank by 3/12/19 Proposal
145 - GARAGE DOORS START END NOTES PHOTO STATUS
- RC
WM Review when JE On Site
146 - START END NOTES PHOTO STSTUS
REFURBISHMENT
PICKET FENCES - RC -t--
Repair & Painting of all Picket Fences - April 2019
WINDSHEILD - 2002 Contacted Gary Mann (RK Contact). He contacted Mercedes Awaiting
MERCEDES reference Windshield Repair - Unable to come up with Solution. Response
Gary was to contact Guard Car Companies, have left a message
requesting update
COMPUTOR - James Ce forwarded History of Existing Library Computer, Feb 2015
LIBRARY - MH
How do you wish to proceed? Awaiting
Response
HVAC • MH Programming Issues resolved. System Running 100% St
Cw
SITE WALLS & MISC Awaiting for Break in Weather
PLASTER WORK -MC
LANDSCAPE - EAST Once Weather Breaks Work will Start on Collapsed Section/Dry
GARDEN Stack Walls & Lavender Beds
Page 5
EFTA00811074
LANDSCAPE - Need to get the Fountain Pit, repowdered where all the lighting
LIGHTING controllers are located
2/18/19 - Work to begin
LAMPS -LODGE Purchased X 4 New Lamps to replace lamps that where broken Complete
during 2018 burglary
Page 6
EFTA00811075
ℹ️ Document Details
SHA-256
d6d6551e9509276aee99937a45dc77552f01b17d2039b3b9b6528176ebf547c8
Bates Number
EFTA00811070
Dataset
DataSet-9
Document Type
document
Pages
6
Comments 0