/2 - WATER START END EST.COST NOTES PHOTO STATUS
DEVELOPMENT
5/6/2014 3/22/19 - Continuing Pumping Water working on the target of
I68afa.
36E - PAVING OF START END EST.COST NOTES PHOTO I STATUS
ROADWAY
6/29/2017 2/12/19 - Gilbert Luna (Universal Paving) & his Forman On Site to
Review Final Section of Work. He Proposed Only to "Fix" 2000' -
MH Z to Bull Head. He indicated Fix for Office to Main Gates.
Proposed Work to begin March.
BG has concerns regarding "Fix" & Proposed Start Date, due to
Temps. Recommend late ApriVMay. BG explained Owner would
want New Surface to Run from MH Z to Cattle Guard RC, Office to
Main Gates
BG indicated a payment of 100k, Gilbert Luna would need to sign
Legal Binder. He expressed concerns as requested work would
cost him approx. 100k. He was to review numbers & get back with
BG. As of date & time no contact has been made.
Should we contact Mountain States or another Company to see if
they are interested in providing a Proposal for a "Fix"?
3/18119 - Received letter from Calvert & Menicucci - collections
agency for Universal Construction, Inc. Forwarded to RK & DI.
13/20/19 - A Complete Timeline, Details, E Mails & Photos x
'forwarded to DI & RK
102 - LUTRON START NOTES PHOTO STATUS
SYSTEM - MH
2/22/2019 '3/12/18 - Lutron Rep On Site. Reviewed system with Randy from Awaiting
RMC Electric. Existing system was designed for local control at the Response from
physical switches not controlled by the Lutron system in the Mech Lutron
Rooms, therefore will be difficult, but not impossible to upgrade.
Lutron are reviewing the options and will forward details within 10
days
118fr PURCHASE START j EST.COST NOTES PHOTO STATUS
WATER TRUCK
Will review with JE On Ske
Page 1
EFTA00811076
118 -PURCHASE START END EST.COST NOTES PHOTO STATUS
GRADER
Will review with JE when On Site
135 START END EST.COST NOTES PHOTO STATUS
REFURBISHMENT
RED HOUSE
1/21/2019 3/20/19 - Stone Work on Fireplace and Pony Wall Started
3/22/19 - Vanity Lights, Toilets, Towel Rails, TV, Lights. Door
Hardware, Fireplace Installed
3/23/19 -"In House"- Clean Up both floors
3/26/19 - Carpet to be Installed
i 35!!L START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
AC SPLIT UNIT &
FURNACE -RED
HOUSE
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove Dispose of x Awaiting
Existing Swamp Cooler. Furnish/Install 1 Carrier 3.5 ton AC Split Response
Unit & Furnace to Red House. RMC Estimate for New Electrical (2/16/191
Circuits & New Electrical Service to Unit
2/16/19 - RK requested 10% Discount
2/19/19 -Airpro Discounted 10%
START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
AC SPLIT UNIT &
FURNACE - LV'S
HOUSE
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing Swamp Cooler. Furnish/Install 1 Carrier 4 ton AC Split Unit Response
& Furnace to LV's House. RMC Estimate for New Electrical Circuits (2/16/191
& Run New Electrical Service to Unit
2116/19 - RK requested 10% Discount
2/19/19 -Airpro Discounted 10%
$4,896.99 2/21/19 - 50% Deposit Paid to Airpro
3/15/19 - 90% Complete, Awaiting Electrical Connect - 3/22/19 -
due to weather delayed to 3/25/19
Page 2
EFTA00811077
139 START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
AC SPLIT UNIT &
FURNACE - YELLOW
HOUSE
2)19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing Swamp Cooler. Furnish/Install 1 Carrier 3 ton Furnace to Response
Yellow House. RMC Estimate for New Electrical Circuits & Run 12/16/191
New Electrical Service to Unit
2/16/19 - RK requested 10% Discount
T
2/19/19 - Airpro Discounted 10%
- TT4,603.59 2/21/19 - 50% Deposit Paid to Airpro
13/15/19 - 90% Complete, Awaiting Electrical Connect - 3/22/19 -
due to weather delayed to 3/25/19
START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
X 6 UNIT HEATERS -
GARAGES RC
2,19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing 6 Heaters. Furnish/Install 6 Sterling Unit Heaters - Response
Garages RC (2/16/191
2/16/19 - RK requested 10% Discount
2119/19 - Airpro Discounted 10%
$8,841.43 2/21/19 - 50% Deposit Paid to Airpro
2/25/19 - Material/Parts Ordered. Installation expected 3/14/19
3/15/19 - Due to weather/road closures. Installation rescheduled
3/25/19
141 - START END EST.COST NOTES PHOTO STATUS
CARPET/TILE/WINDO
W TREATMENTS -
LODGE
3/15/2019 3/19/19 - Carpet Removed - "In House"
3/20/19 - All Light Fixtures, Electrical Covers, Air Vents, Ducts
Removed - "In House"
3/22/19 - Native Son On Site to review window treatments
3/25/19 - Patching/Priming of all Walls. Trim & Ceilings to Begin
Page 3
EFTA00811078
142 - PHONE SYSTEM . START END EST.COST NOTES PHOTO STATUS
LODGE & LOG
Project Placed On Hold 1/10/18
Are we still to proceed with Verizon Cellular Phone Line for Lodge? Awaiting
Response
lAre we still to proceed with Verizon Cellular Phone Line & Solar Awaiting
Generator for Log Cabin? Response
143 _.SECURITY START END EST.COST NOTES PHOTO STATUS
CAMERAS -FRONT
GATES
3/13/19 - Purchased Verizon Cellular Security Camera - 30 day trail
- $20.00 a month
3/14/19 - Camera Installed, at present linked to Brice, cell
phone & I Pad. Working very well. Will forward update 3/22/19
3/22/19 - System is working out very well, no issues. Will purchase
another Camera to install on 2nd gate
144 - SEPTIC START END EST.COST NOTES PHOTO STATUS
SYSTEMS -RC
2/28/2019 Septic Line to the Tank & the Leaching Field for the BH need
replacing. Roots from Trees have Compromised the Line. The
Adobe is in the same situation
2/28/19 - All RC Septic Tanks, Pumped Out
Gene Basset will forward a Proposal for Removal/Installation New
Septic Tank by 3/22/19
3/21/19 - Gene Bassett on site needed to obtain more Awaking
measurements to obtain detailed Proposal, which he hopes to have Proposal
by 3/28/19
145 - GARAGE DOORS START END EST.COST NOTES PHOTO STATUS
- RC
Will Review when JE On Site
146 - START END EST.COST NOTES PHOTO STSTUS
REFURBISHMENT
PICKET FENCES - RC
Repair & Painting of all Picket Fences - April 2019
$166.82 Purchased 100 Cedar Pickets - Curing in Garages
Page 4
EFTA00811079
X17 - SITE WALLS & START END EST. COST NOTES PHOTO STATUS
MISC PLASTER
WORK MC
Expect Bid by 3/22/19 - Work would not start until late April/May
-NEW PATHWAY- START END NOTES PHOTO STATUS
LOG CABIN
2/15/2019 3/22/2019 1 2/16/19- Existing Stone Pathway Removed
$3,144.39 2/20/19 - Deposit x 65 3x12x6 Rough Pine A platform will need to
be constructed under pathway to keep it level
$1,287.69 3/7/19 - Balance Rough Pine
$434.20 3/13/19 - Purchase Lag Screws/Washers/Boring Kit 30 2x4x8
Treated Lumber for Path Foundation
3/14/19 - Rough Pine On Site
3/19/19 - Project to begin
3/22/19 - Project Complete - x 8 support caps will be removed once
Pine has weather for a few weeks then Sealer/Stain applied to
matching existing steps
Car
START END EST.COST NOTES PHOTO STATUS
REFURBISHMENT
OUTSIDE LOG CABIN
Logs Require Sanding. Cleaning, Water Sealing & Replacement of
Chinking. Will begin in the Spring
150 • WINDSHEILD - START END EST.COST NOTES STATUS
2002 MERCEDES PHOTO,
2/13/2019 Contacted Gary Mann (RK Contact). He contacted Mercedes
reference Windshield Repair - Unable to come up with Solution.
Gary was to contact Guard Car Companies, have left a message
requesting update
3/22/19 - As of Date & Time No Solution on how to Repair
Windshield has been found. Will continue investigating
COMPUTOR - James Ce forwarded History of Existing Library Computer, Feb 2015
LIBRARY - MH
How do you wish to proceed? Awaiting
Response
Page 5
EFTA00811080
LANDSCAPE - EAST Once Weather Breaks Work will Start on Collapsed Section/Dry
GARDEN Stack Walls & Lavender Beds
Page 6
EFTA00811081
ℹ️ Document Details
SHA-256
81921bbdc04496d1dcc58d262ca9c84a0d6666355f516c3f76e2a1b84557bc3e
Bates Number
EFTA00811076
Dataset
DataSet-9
Document Type
document
Pages
6
Comments 0