New Engineering Building Pad
Material Outside Vendor Labor Shipping Trucking
Temp Enclosure/safety
Material Handling
Equipment Rental $1,500.00
Misc Expenses $1,000.00
Layout/Survey
Earthwork and Demo $1,300.00 $2,000.00
Site Drawings
Pest Control
Site Dranage $1,000.00
Pipes/Utilities $500.00
Concrete $9,950.00 $500.00 $8,500.00 $2,500.00
Vapor Barrier $200.00
Ties/Accessories/bolts $1,500.00
Rebar $1,400.00
Saw Cutting $250.00
Curing/Protection $300.00
Fine Grade $1,000.00
Wood/Formwork $1,200.00 $4,500.00
Fastners $400.00
Sub Totals $18,700.00 $3,300.00 $13,000.00 $4,500.00
Total $39,500.00
Note: Labor # is for outside labor only/ finish concrete crew
Note: Rebar is for additional rebar
Note; This is a basic pad
No Utilities, septic sysyem, electrical, wall, or engineering yard work
The pad will have 3 gray water drains. The pad will not have sanitary drains
Includes min work on electrical vault
EFTA01109772
Tax
EFTA01109773
ℹ️ Document Details
SHA-256
fdae9d094f34494dcf3a6db74610c983201eed95d5d48d56f86392afe3bf7db2
Bates Number
EFTA01109772
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0