EFTA01109771
EFTA01109772 DataSet-9
EFTA01109774

EFTA01109772.pdf

DataSet-9 2 pages 125 words document
Open PDF directly ↗ View extracted text
👁 1 💬 0
📄 Extracted Text (125 words)
New Engineering Building Pad Material Outside Vendor Labor Shipping Trucking Temp Enclosure/safety Material Handling Equipment Rental $1,500.00 Misc Expenses $1,000.00 Layout/Survey Earthwork and Demo $1,300.00 $2,000.00 Site Drawings Pest Control Site Dranage $1,000.00 Pipes/Utilities $500.00 Concrete $9,950.00 $500.00 $8,500.00 $2,500.00 Vapor Barrier $200.00 Ties/Accessories/bolts $1,500.00 Rebar $1,400.00 Saw Cutting $250.00 Curing/Protection $300.00 Fine Grade $1,000.00 Wood/Formwork $1,200.00 $4,500.00 Fastners $400.00 Sub Totals $18,700.00 $3,300.00 $13,000.00 $4,500.00 Total $39,500.00 Note: Labor # is for outside labor only/ finish concrete crew Note: Rebar is for additional rebar Note; This is a basic pad No Utilities, septic sysyem, electrical, wall, or engineering yard work The pad will have 3 gray water drains. The pad will not have sanitary drains Includes min work on electrical vault EFTA01109772 Tax EFTA01109773
ℹ️ Document Details
SHA-256
fdae9d094f34494dcf3a6db74610c983201eed95d5d48d56f86392afe3bf7db2
Bates Number
EFTA01109772
Dataset
DataSet-9
Document Type
document
Pages
2

Comments 0

Loading comments…
Link copied!